Year: 2016

October 2016

NOMARCHIA Station: The waterproofing of masonry walls from the foundation slab to level -1 has been completed, while in progress is the construction of the platform. NOMARCHIA Crossover: The waterproofing of masonry walls from the foundation slab to level -1 has been completed. In progress is the construction of scaffolding…
Μάθε Περισσότερα

October 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress is the archaeological excavation at the southeast and southern shaft, as well as the installation of escalators. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while there are still in progress at the southern part. DIMOKRATIAS Station:…
Μάθε Περισσότερα

October 2016

NIKEA Station: The works for the construction of industrial floors at the concourse level of the Station are in progress. In addition, in progress is the construction of the permanent lining of the main station (phase B’): construction of exterior perimeter walls at the E/M level of the floor slab…
Μάθε Περισσότερα

September 2016

At Ethnarchou Makariou Street, in progress are works for the relocation of the rainwater drainage pipe. At Mikras Asias street, completed are the works for the construction of the tramway corridor from Papandreou Bridge past Sarantaporou Street. The urban planning of the area and Mikras Asias stop is completed. At…
Μάθε Περισσότερα

September 2016

NOMARCHIA Station: The works for the construction of the foundation slab have been completed. The construction of the permanent lining from the foundation slab up to level -1 is in progress. Nomarchia Junction: The construction of the foundation slab is completed. The removal of the struts at the last level…
Μάθε Περισσότερα

September 2016

NEW RAILWAY Station: Excavation works at the southern access are in progress. DIMOKRATIAS Crossover: The works for the construction of the foundation micro-piles are in progress. DIMOKRATIAS Station: Traffic arrangements at Monastiriou Street have been completed. The works for the construction of the raft are in progress while archaeological excavations…
Μάθε Περισσότερα

September 2016

Komninou Shaft: The works for the worksite installations have been completed. Excavation and temporary retaining works are in progress. AGHIA VARVARA Station: Backfilling works are in progress. At Taxiarchon Shaft, the construction and concreting of the foundation slab are completed. KORYDALLOS Station: Filling works and works related to industrial and…
Μάθε Περισσότερα

August 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor at Papandreou Bridge. At Grigoriou Lambraki street, the construction of the tramway corridor from the U-turn up to Venizelou Street, along with the urban planning of Lambraki and Evangelistrias stops are completed. The construction…
Μάθε Περισσότερα

August 2016

NOMARCHIA Station: The works for the construction of the foundation slab are in progress. KALAMARIA Station: The works for the temporary retaining of the metal struts up to the 4th level are in progress. ARETSOU Station: The installation of metal struts at the 2nd level has been completed. In progress…
Μάθε Περισσότερα

August 2016

NEW RAILWAY Station: The works for the construction of retaining piles in the shafts and the diversion of the combined-flow network are in progress. DIMOKRATIAS Station: the excavation works are completed, while in progress are the preparatory works for the subsequent traffic phase. AGHIA SOFIA Station: The works for the…
Μάθε Περισσότερα