Year: 2016

August 2016

Komninou Shaft: The works for the worksite installations (building crane, settlement tank installation) are in progress. AGHIA VARVARA Station: The works for the construction of slabs at all levels are completed. At M. Alexandrou Shaft, completed is the worksite installation, while in progress are excavation and temporary retaining works. NIKEA…
Μάθε Περισσότερα

June 2016

NOMARCHIA Crossover: The works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. KALAMARIA Station: The installation of metal struts at the 2nd level have been completed. In progress are the excavation works…
Μάθε Περισσότερα

June 2016

Dimokratias Crossover: Works for the excavation of the final level are in progress. DIMOKRATIAS Station: Completion of the construction of slab -2. Moreover, in progress is the archaeological excavation of the final level. SINTRIVANI Station – REPORT: In progress is the temporary retaining of the northern access. PAPAFI Station: In…
Μάθε Περισσότερα

June 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor from Papandreou Bridge up to Sarantaporou street. In progress are the works for the construction of the tramway corridor from Sarantaporou street up to Lambraki Bridge with the U-turn as well as the urban…
Μάθε Περισσότερα

June 2016

AGHIA VARVARA Station: The works for the removal of the precast segments of the false tunnel and the last ring have been completed. Works for the industrial floors and fillings are in progress. At M. Alexandrou Shaft, in progress are the excavation and temporary retaining works. NIKEA Station: The works…
Μάθε Περισσότερα

May 2016

NOMARCHIA Station: The excavation of level -3 of the station, as well as the works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert. NOMARCHIA Crossover: The excavation works of level -3 have…
Μάθε Περισσότερα

May2016

At the beginning of the extension, at the NATM double track tunnel, phase A’ of the tunnel excavation from TBM shaft to Aghia Marina is in progress. At Komninou shaft, the PUO network diversions and the archaeological trenches have been completed, while the works related to the worksite occupation and…
Μάθε Περισσότερα

May 2016

At Mikras Asias street, in progress are the works for the construction of the tramway corridor (from Papandreou bridge up to the U-turn), as well as the urban planning works at the adjacent sidewalk. At Grigoriou Lambraki street, the construction of the tramway corridor at the section extending between Distomou…
Μάθε Περισσότερα

May 2016

Dimokratias Crossover: The works for the installation of struts at the final level are in progress. DIMOKRATIAS Station: Completion of excavation works at level -2 of the station. In progress is the construction of slab -2. Moreover, in progress is the archaeological excavation of the northern access, the northern ventilation…
Μάθε Περισσότερα

MEMORANDUM OF UNDERSTANDING AND COOPERATION FOR IN-SITU DISPLAY OF ANTIQUITIES IN VENIZELOU STATION OF THESSALONIKI METRO

A Memorandum of Understanding and Cooperation (MoU) was signed on Thursday June 16th among the Ministry of Culture and Sports, the Ministry of Transport, Infrastructure and Networks (POMEDI), ATTIKO METRO S.A. and the Thessaloniki Municipality whose scope is the formulation of a framework of cooperation for the in-situ display of…
Μάθε Περισσότερα