PROGRESS OF WORKS

May 2018

A. With regard to the TRAMWAY CORRIDOR:

• At Piraeus:
– The following activities are in progress, which complete the Tramway Line extension to Piraeus: the construction of the Tramway corridor at Vas. Georgiou street (from the end of Tinaneios (Tinan) garden to Akti Miaouli), at Akti Miaouli pedestrian crossing and at Possidonos Ave., as well as the installation of overhead contact line in the areas where the Tramway corridor has been completed.

B. With regard to other works:

– Vas. Georgiou street (Roloi square): after the completion of the excavations (retaining and earthworks, insulations), concreting works begun for the construction of the new Tramway traction power substation
– Ethn. Antistaseos street (Ippodameias square): after the implementation of the final traffic arrangement, urban planning works were completed (traffic island etc.)
– SEF stop and Alikakou square: the construction of the various foreseen installations (serving SEF stop) is in progress
– In progress are works for the installation of underground waste bins.

Print Friendly, PDF & Email

February 2018

A. With regard to the TRAMWAY CORRIDOR:

In the remaining areas of the entire Tramway network:

• Tramway corridor works have been completed:

– at N. Faliro stop (installation of turnouts and connection of the Tramway extension to Piraeus with the operating tramway network)
– at Mousson Street (installation of a turnout for optimum operation of the Tramway extension to Piraeus)
– at Syntagma (amended terminal stop)

• In progress are works for the completion of the urban planning at Syntagma terminal stop.

B. With regard to other work fronts:

• Along the Tramway corridor, in progress are:

– works for the maintenance of manholes on asphalt road pavements
– the installation of tramway signalling system at signalled junctions located along the tramway corridor.

• At Akti Possidonos Street, in progress are:

– archaeological excavation works
– works for the relocation of PUO networks, the construction of tramway corridor and urban planning.

• At Vas. Georgiou & Ethn. Antistasseos junction in progress are:

– archaeological excavation works
– works for the relocation of PUO networks, the construction of tramway corridor.

• SEF stop and Alikakou square:
– planting and urban planning works have been completed.
– works for the construction of other foreseen structures (serving the needs of the stop, etc.).

• In various Piraeus areas, in progress are works for the installation of underground waste bins.