PROGRESS OF WORKS

February 2014

  • Traffic arrangements were implemented in the central district of Piraeus Municipality;
  • The works for the relocation of trolley-bus lines (lines 16, 17 and 20) outside the Piraeus Tramway extension path are in progress;
  • In building 2 of the of Elliniko Tramway Depot building installations, the works related to its architectural finishes have been completed and the E/M installations are at the completion and testing phase, while the works for the re-arrangement of building 1 room areas are in progress;
  • In the children playground area at Rizarios – Palaio Faliro, the bearing structure and the brick structure have been completed, the architectural finishing works in the WC buildings are in progress, while the works for the construction of the landplot fencing and the configuration of the surrounding area are in progress.
Print Friendly, PDF & Email

January 2014

  • Works related to traffic arrangements have commenced in the central area of Piraeus region;
  • Works for the relocation of Trolley-bus lines from the Tramway extension line to Piraeus have commenced (Relocation of Trolley-bus network (Line 20) to 2asMerarhias street);
  • At the building facilities of the Tramway Depot at Elliniko, in building 2, the architectural finishes’ works are at a completion stage and the E/M installations are at a testing phase, while the works for the re-arrangement of areas in building 1 are in progress;
  • In the landplot of the playground, in the area of Rizareios-P. Faliro, the bearing structure has been completed and the architectural finishes’ works in the WC building complex are in progress; moreover, the construction of the landplot fencing is in progress.