PROGRESS OF WORKS

January 2017

• At Ethnarhou Makariou street, in progress is the construction of Karaiskaki stop and the staircase connecting this stop with the underground pedestrian walkway.

• At Papandreou bridge and at Micras Asias Street, at the completion stage are the works for the construction of the tramway corridor (fitting of rails), as well as pending works in the pocket area and the transition area from Papandreou bridge to Micras Asias street.

• At Grigoriou Lambraki street, street lighting works have commenced and are soon to be completed. Tramway corridor construction works from the U-turn of Lambraki street to Venizelou street have been completed, while in progress is the construction of the tramway corridor from Venizelou street to Vas. Georgiou Street (trackwork of the main line has been completed, while at a completion stage are the works in the pocket area and the rail installation works on the main line and the pocket).

• At Vas. Georgiou street, in progress is the construction of the Tramway corridor from Alkiviadou street to the crossing on Iroon Polytechniou street.

• At Ethnikis Antistaseos street, the urban planning works at Aghia Triada stop have been completed and in progress are the works for the construction of Ippodamias stop. The construction of the tramway corridor trackwork from Georgiou street to Ippodamias street have been completed.

• On Omiridou Skylitsi street, in progress are the works for the construction of Androutsou and Omiridou Skylitsi stops.

(the reference to the “adjacent” or “facing” sidewalk relates to the actual location of the tramway corridor).

Print Friendly, PDF & Email

December 2016

• At Papandreou bridge and at Mikras Asias Street, the tramway corridor at the section extending from Papandreou bridge to Gr. Lambraki entrance (after the U-turn) has been completed and tracks are currently installed in the pocket area.

• At Grigoriou Lambraki street, the urban planning works at the facing sidewalk from the U-turn of Lambraki street to Venizelou street, have been completed. Tramway works are at a completion stage outside the pocket area from Venizelou Street to Vas. Georgiou Street.

• At Vas. Georgiou street, the urban planning works at the facing sidewalk, at the section from Gr. Lambraki street to Alkiviadou street, have been completed. Completed is the tramway corridor from Gr. Lambraki to Alkiviadou Street, while in progress is the archaeological excavation at DIMARCHIO stop namely from Iroon Polytechniou to Filonos street as well as in the R/S construction area (Roloi).

• At Ethnikis Antistaseos street, the works for the construction of Aghia Triada stop, the archaeological works in the area of Ippodamias stop, as well as the construction of the tramway corridor trackwork from Tsamadou to Ippodamias street have been completed.

• At Omiridou Skylitsi street, in progress are the works for the relocation of the PUO works (from Lambraki bridge to Tzavella street) as well as the tramway corridor construction works.

• At SEF stop and Alikakou Square, in progress are the works for the construction of the tramway corridor and for the reconstruction of the stop.

(the reference to the “adjacent” or “facing” sidewalk relates to the actual location of the tramway corridor).