Project progress

Project progress

PROGRESS OF WORKS

February 2016

  • In progress are the relocations of the water supply networks at the sidewalk adjacent to Grigoriou Lambraki street, OTE & Fiber Optics networks at Ethn. Antistaseos street, Sewage & EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk adjacent to Ethnikis Antistasseos street.
  • In the area of Evangelistria, at Grigoriou Lambraki street, during the excavation of the tramway corridor, archaeological finds were revealed and a wide archaeological excavation was conducted.
  • Trackwork construction works in a continuous linear configuration are in progress from Papandreou bridge up to the middle of Grigoriou Lambraki Street (through M. Asias Street and Lambraki Street reversing). The works for the installation of tracks have commenced; they have been installed at a length of approximately 200m at Mikras Asias street (after Papandreou bridge); the installation of tracks at Grigoriou Lambraki street (from Lambraki bridge towards Pylis street) has commenced.
    Moreover, works are in progress for the construction of Tramway stops on Mikras Asias street and at Gr. Lambraki bridge. Catenary poles foundation works are in progress on Grigoriou Lambraki, Ethnikis Antistaseos and Vassileos Grigoriou Streets. Works at Lambraki pedestrian bridge are in progress along with the works for the connection of Karaiskaki stop to the existing underground passage.
  • The urban planning works at the sidewalk adjacent to Ethinikis Antistasseos Street (already completed at two building blocks), at the opposite sidewalk at Vassileos Georgiou Street (already completed at four building blocks) and at the sidewalk adjacent to Grigoriou Lambraki street (from Lambraki bridge up to Pylis street) are in progress.
    (The reference “opposite” and “adjacent sidewalks” is related to the Tramway traffic).
Print Friendly, PDF & Email

January 2016

  • Completed are the relocations of sewage, PPC & and EPA networks at the sidewalk adjacent to Grigoriou Lambraki street, Sewage, EPA & Fiber Optics at Vassileos Georgio street and the ILPAP abolished lines dismantling works at Vassileos Georgiou street.
  • In progress are the relocations of the water supply networks at the sidewalk adjacent to Grigoriou Lambraki street, EPA networks at Akti Possidonos, OTE & Fiber Optics networks at Ethn. Antistaseos street, Sewage & EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk adjacent to Ethnikis Antistasseos street.
  • The archaeological excavation at the PUO relocation trenches on Grigoriou Lambraki street is in progress.
  • Trackwork construction works in a continuous linear configuration are in progress from Papandreou bridge up to the middle of Grigoriou Lambraki Street (through M. Asias Street and Lambraki Street reversing). Works are in progress for the construction of Tramway stops on Mikras Asias street and at Gr. Lambraki bridge. Catenary poles foundation works are in progress on Grigoriou Lambraki, Ethnikis Antistaseos and Vassileos Grigoriou Streets. Works at Lambraki pedestrian bridge are in progress along with the works for the connection of the pedestrian passage at Karaiskaki stop to the existing underground passage.
  • The urban planning work at the sidewalk adjacent to Mikras Asia and on Lambraki Street reversing are at the completion stage, while the respective works at the sidewalk adjacent to Ethinikis Antistasseos Street and at the opposite sidewalk at Vassileos Georgiou Street are in progress.