Project progress

Project progress

PROGRESS OF WORKS

December 2013

  • The organization of individual worksites at several locations along the Tramway Extension to Piraeus (Lambraki Avenue U-turn, Karaiskaki Bridge) has commenced;
  • Works for replacing the canopy of the workshop at Building No. 1 have been completed; architectural finishes and electromechanical works at Building No. 2 are at an advanced stage; dismantling works in areas of Building No. 1, in the Tramway Depot Building facilities in Elliniko, are in progress;
  • The works for the completion of the bearing structure of the W.C. building complex in the land plot of the playground in the area of Rizareios – P. Faliro are at an advanced stage.
Print Friendly, PDF & Email

November 2013

  • The topographical survey works in roads and sidewalks along the Tramway Extension to Piraeus are at an advanced stage;
  • Architectural finishes and electromechanical works at Building No. 2 are in progress, while the dismantling works in the areas of Building No. 1 to be re-configured in the Tramway Depot Building facilities in ELLINIKO have commenced;
  • Cleaning works in the land plot of the playground in the area of Rizareios – P. Faliro have been completed; while the works related to the W.C. building complex have commenced.
Print Friendly, PDF & Email