Piraeus

Piraeus

On November 21st 2008 ATTIKO METRO S.A. proceeded to the re-procurement of the project related to Line 3 Metro extension to the Western Suburbs, terminating in the area of Piraeus (underground tunnel, 7.6 km long, with 6 modern stations: Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus, Dimotiko Theatro).

On February 13th 2009, 6 technical consortia/joint ventures expressed their interest in the construction of the project. On October 5th 2011, ATTIKO METRO S.A. proceeded to the unsealing of the Financial Offers for the Project concerning the extension of Metro Line 3 to Piraeus.

The classification order of the three bidding joint ventures, based on their Financial Offer, is as follows:

JOINT VENTUREFINANCIAL OFFER
1. J&P – ΑVΑX ΑΕ – GHELLA SPA – ALSTOM TRANSPORT SA343.96 million €
2. AKTOR ΑΤΕ – ΤΕRΝΑ ΑΕ349.00 million €
3. FCC CONSTRUCCION S.A. – ALPINE BAU GMBH349.75 million €

Based on the aforementioned Tender results, J&P – ΑVΑX S.A. – GHELLA SPA – ALSTOM TRANSPORT SA is the lowest-bidder of the Tender.

On March 1st 2012, the relevant contract was signed with the contracting joint venture J&P – AVAX S.A., GHELLA SPA, ALSTROM TRANSPORT S.A for the construction of Line 3 extension from Aghia Marina to Piraeus, 7.6 km long in total, with 6 modern Metro Stations. Attiko Metro S.A. was represented by Mr. Christos Tsitouras, Chairman of the BoD and Managing Director, while the Construction Joint Venture J&P ΑVAX SA was represented by Mr. Konstantinos Mitzalis, Managing Director.

This Project constitutes a 730,000,000 EURO investment in areas of Piraeus Municipalities and other Municipalities in the wider area (Nikea, Korydallos, Aghia Varvara), which are currently faced with acute traffic problems and sub-standard services, in terms of Public Transport Modes.

The Metro Extension to Piraeus will serve approximately 132,000 passengers on a daily basis, while the distance between the Port and the International Airport will be covered by the Metro in just 45 minutes. Additionally, once the Metro becomes operational, the number of vehicles will be reduced by approximately 23,000 on a daily basis, leading to a respective daily reduction in CO2 by 120 tn.

Especially as regards Piraeus Station, a major Transportation Junction will emerge, connecting the two Metro Lines (Line 1 and Line 3), the Port, the Suburban Railway and the Tramway, which is also foreseen to pass through the same area, providing, thus, inter-modal transfers.

The Metro tunnel will be constructed using a Tunnel Boring Machine (TBM) in order to minimize the inevitable disturbance to the functions of the Municipalities; during the construction period (2012-2017) 2,000 persons in total are foreseen to be employed in this Project.

The extension of the Tramway from Neo Faliro to Piraeus centre recently commenced, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway network. More specifically, in January 2013 the contract was signed between ATTIKO METRO S.A. and the Company THEMELI S.A.

Apart from the Line 3 Extension to Piraeus, ATTIKO METRO S.A will shortly be engaged in the following projects as well, namely:

  1. Extension of the Tramway network from Neo Faliro to Piraeus centre, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway. The construction of this specific project commenced in September 2013 by ATTIKO METRO.
  2. Conversion of Line 1 (ISAP) section form N.Faliro to Piraeus into an underground structure, with the addition of one new station in the area of Keranis Factory, unifying, in terms of functions and town planning the areas of Piraeus currently served by the surface ISAP Line 1. The designs pertaining to this Project are about to be completed enabling, thus, ATTIKO METRO S.A. to put it to Tender.
  3. Extension to the Tramway Network to Keratsini – Perama, following an underground alignment at a large part of Keratsini Municipality, running along the alignment of the old Perama tramway. The Advanced Concept Designs regarding this Project are underway.
LINE 3 EXTENSION TO PIRAEUS
Location of the Stations

Aghia VarvaraEleftheriou Venizelou Av. (Ag. Eleoussa)
KorydallosEleftherias Square
NikaiaEl.Venizelou Square
ManiatikaEtolikou & Mavromihali Str.
PiraeusPort (close to ISAP station)
Dimotiko TheatroIroon Polytechniou & Vassileos Georgiou

Tunnel

6,5km of the tunnel of the extension will be constructed using the Tunnel Boring Machine, while the remaining parts at the beginning and at the end of the project will be constructed via the underground excavation method.

Shafts

8 ventilation shafts in total shall be constructed along the new Line and two shafts for the TBM’s entering/exiting.

PROGRESS OF WORKS

February 2018

• AGHIA VARVARA Station – Doors painting works and waterproofing works are in progress.

• KORYDALLOS Station – Access 2 excavation works are in progress.

Pissidias shaft: Excavation works and works for the installation of the temporary retaining system, foundation improvement and temporary retaining works have been completed. Excavation works and works for the temporary retaining of NATM ventilation tunnel are in progress.

• NIKEA Station – NATM ventilation tunnel: Final floor level (reverse arch) waterproofing works are in progress.

Tzavela shaft: the works for the construction of the building crane foundation base are in progress.

• MANIATIKA Station – South shaft (Koumoundourou street): The works for the excavation and temporary retaining of the open trench have been completed, while the works for the excavation and temporary retaining of the NATM tunnel are in progress.

• MANIATIKA Station – North shaft (Dimitrakopoulou street): The installation of the building crane has been completed; works for the excavation – temporary retaining of the shaft at level -4 are in progress.

• PIRAEUS Station: Jet grouting at the joints of the diaphragm walls has been implemented. In progress are excavation works at the main Station (works at level -2 have been completed), as well as works for the installation and prestressing of struts for the temporary retaining of at levels 1 and 2.

• DIMOTIKO THEATRO Station: in progress are the works for the construction of main entrance and shafts terminations (street level) and secondary concreting works at the E/M level (level -1).

South Staircase: Concreting works of the vault permanent lining are in progress.

Korai square access gallery: in progress are the works for the installation of reinforcement at the walls and vault of the permanent lining

Bakogianni square access gallery: Permanent lining concreting works in progress.

Deligianni shaft: The works for TBM disassembly are in progress.

Panepistimio shaft: The works for the excavation and temporary retaining of the shaft down to level -4.30 (9th excavation level) are in progress.

The excavation of all tunnels is 100% completed.

Print Friendly, PDF & Email

January 2018

• TBM access shaft: The works for the construction and waterproofing of perimeter walls has been completed.

• AGHIA VARVARA Station – M. Alexandrou shaft: The works for the permanent lining of the shaft’s wall are in progress.

• KORYDALLOS Station – Pissidias shaft: Excavation and temporary retaining works (levels 1 to 5) have been completed; excavation works and works for the disposal of excavation spoil (level 6) are in progress.

• NIKEA Station: Backfilling works at the Station, at street level, as well as works for the removal of the piles’ cap beam are in progress.

• MANIATIKA Station: At the Station’s open trench, in progress are the works for the permanent lining of the foundation and the works for the permanent lining of walls from the foundation level to the E/M slab level (level -3).

• MANIATIKA Station – South shaft (Koumoundourou street): The works for the excavation and temporary retaining of level 9 have been completed, while the works for the excavation and temporary retaining of level 10 are in progress.

• MANIATIKA Station – North shaft (Dimitrakopoulou street): The works for the construction of the building crane foundation base have been completed.

• PIRAEUS Station: In progress are excavation works at levels 1 and 2 of the main Station, as well as works for the installation and prestressing of struts for the temporary retaining of level 1.

• DIMOTIKO THEATRO Station – South Staircase: Concreting works of permanent lining walls have been completed.

Bakogianni square access tunnel: The installation of walls and vault reinforcement is in progress.

Deligianni shaft: The works for the configuration of the surface for the TBM dismantling are in progress.

Panepistimio shaft: The works for the excavation and temporary retaining of the shaft down to level +1.30 are in progress.

The excavation of all tunnels has been completed by 100%.