Piraeus

Piraeus

On November 21st 2008 ATTIKO METRO S.A. proceeded to the re-procurement of the project related to Line 3 Metro extension to the Western Suburbs, terminating in the area of Piraeus (underground tunnel, 7.6 km long, with 6 modern stations: Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus, Dimotiko Theatro).

On February 13th 2009, 6 technical consortia/joint ventures expressed their interest in the construction of the project. On October 5th 2011, ATTIKO METRO S.A. proceeded to the unsealing of the Financial Offers for the Project concerning the extension of Metro Line 3 to Piraeus.

The classification order of the three bidding joint ventures, based on their Financial Offer, is as follows:

JOINT VENTUREFINANCIAL OFFER
1. J&P – ΑVΑX ΑΕ – GHELLA SPA – ALSTOM TRANSPORT SA343.96 million €
2. AKTOR ΑΤΕ – ΤΕRΝΑ ΑΕ349.00 million €
3. FCC CONSTRUCCION S.A. – ALPINE BAU GMBH349.75 million €

Based on the aforementioned Tender results, J&P – ΑVΑX S.A. – GHELLA SPA – ALSTOM TRANSPORT SA is the lowest-bidder of the Tender.

On March 1st 2012, the relevant contract was signed with the contracting joint venture J&P – AVAX S.A., GHELLA SPA, ALSTROM TRANSPORT S.A for the construction of Line 3 extension from Aghia Marina to Piraeus, 7.6 km long in total, with 6 modern Metro Stations. Attiko Metro S.A. was represented by Mr. Christos Tsitouras, Chairman of the BoD and Managing Director, while the Construction Joint Venture J&P ΑVAX SA was represented by Mr. Konstantinos Mitzalis, Managing Director.

This Project constitutes a 730,000,000 EURO investment in areas of Piraeus Municipalities and other Municipalities in the wider area (Nikea, Korydallos, Aghia Varvara), which are currently faced with acute traffic problems and sub-standard services, in terms of Public Transport Modes.

The Metro Extension to Piraeus will serve approximately 132,000 passengers on a daily basis, while the distance between the Port and the International Airport will be covered by the Metro in just 45 minutes. Additionally, once the Metro becomes operational, the number of vehicles will be reduced by approximately 23,000 on a daily basis, leading to a respective daily reduction in CO2 by 120 tn.

Especially as regards Piraeus Station, a major Transportation Junction will emerge, connecting the two Metro Lines (Line 1 and Line 3), the Port, the Suburban Railway and the Tramway, which is also foreseen to pass through the same area, providing, thus, inter-modal transfers.

The Metro tunnel will be constructed using a Tunnel Boring Machine (TBM) in order to minimize the inevitable disturbance to the functions of the Municipalities; during the construction period (2012-2017) 2,000 persons in total are foreseen to be employed in this Project.

The extension of the Tramway from Neo Faliro to Piraeus centre recently commenced, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway network. More specifically, in January 2013 the contract was signed between ATTIKO METRO S.A. and the Company THEMELI S.A.

Apart from the Line 3 Extension to Piraeus, ATTIKO METRO S.A will shortly be engaged in the following projects as well, namely:

  1. Extension of the Tramway network from Neo Faliro to Piraeus centre, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway. The construction of this specific project commenced in September 2013 by ATTIKO METRO.
  2. Conversion of Line 1 (ISAP) section form N.Faliro to Piraeus into an underground structure, with the addition of one new station in the area of Keranis Factory, unifying, in terms of functions and town planning the areas of Piraeus currently served by the surface ISAP Line 1. The designs pertaining to this Project are about to be completed enabling, thus, ATTIKO METRO S.A. to put it to Tender.
  3. Extension to the Tramway Network to Keratsini – Perama, following an underground alignment at a large part of Keratsini Municipality, running along the alignment of the old Perama tramway. The Advanced Concept Designs regarding this Project are underway.
LINE 3 EXTENSION TO PIRAEUS
Location of the Stations

Aghia VarvaraEleftheriou Venizelou Av. (Ag. Eleoussa)
KorydallosEleftherias Square
NikaiaEl.Venizelou Square
ManiatikaEtolikou & Mavromihali Str.
PiraeusPort (close to ISAP station)
Dimotiko TheatroIroon Polytechniou & Vassileos Georgiou

Tunnel

6,5km of the tunnel of the extension will be constructed using the Tunnel Boring Machine, while the remaining parts at the beginning and at the end of the project will be constructed via the underground excavation method.

Shafts

8 ventilation shafts in total shall be constructed along the new Line and two shafts for the TBM’s entering/exiting.

PROGRESS OF WORKS

May2016

  • At the beginning of the extension, at the NATM double track tunnel, phase A’ of the tunnel excavation from TBM shaft to Aghia Marina is in progress.
    At Komninou shaft, the PUO network diversions and the archaeological trenches have been completed, while the works related to the worksite occupation and installations are in progress.
  • AGHIA VARVARA Station: At Taxiarchon shaft, the construction of piles and the cap beam, as well as the construction and tensioning of prestressed anchors were completed. The works for the excavation at the final level of the shaft are in progress.
  • NIKEA Station: The works for the construction of non-bearing masonry walls at level -2 of the concourse level slab and at level -3 of the platform slab, as well as the masonry plastering works at level -1 of the E/M floor are in progress.
    At the northern entrance, Phase 2 of the traffic diversion has been completed. Moreover, the excavation and removal of excavation spoils at the 1st level, the application of shotcrete at the 1st level of the excavation and the installation of metal tubed struts at the 1st level of the excavation were completed. In progress are the excavation works and the works for the removal of excavation spoils at the 2nd level.
  • PIRAEUS Station: In progress are the works for the drilling of soldier piles with the use of jet grouting at the northern entrance and the works for the connection of the sewage/storm water shaft of ISAP Depot with the network at Kononos street.
  • DIMOTIKO THEATRO Station: In the main station, the works for the installation of wall reinforcement from the concourse level up to the E/M level, as well as the concreting works at the concurse level, are in progress.
    In the underground section of the station, the 3rd phase excavation-temporary retaining works (invert) (progress: 46.545m/46.545m) were completed, while in progress are the works for the removal of protruding parts of shotcrete.
    At Dimotiko Theatro ventilation shaft, the construction of the piles cap beam was completed, while the 1st level excavation works are progress.
    In the NATM triple track tunnel towards the University of Piraeus, the Phase A’ and B’ excavation works (excavation progress: 116.61/140m.) are in progress.
    In the NATM triple track tunnel towards DIMOTIKO THEATRO, Phases A’ and B’ excavation works were completed, Phase D’ excavation works (INVERT) (33/63m) are in progress.
    The tunnel excavation has been completed by 58.23%.
Print Friendly, PDF & Email

March 2016

  • AGHIA VARVARA Station: The construction of the ticketing level slab was completed.
    At Taxiarchon shaft, the excavation of the 7th level was completed.
  • NIKEA Station: The works for the permanent lining of the station were completed. More specifically:
    construction of the invert (reverse arch)
    construction of side walls
    construction of the vault
    In addition, the works for the construction of non-bearing masonry walls at the E/M level are in progress.
    At the northern entrance, in progress are the excavation works up to the lower side of the pile cap beam and the works for the construction of piles.
  • MANIATIKA Station: In the main tunnel of the station, the excavation and temporary retaining Phase b of the access chamber are in progress.
  • PIRAEUS Station: The construction of diaphragm walls is in progress.
  • DIMOTIKO THEATRO Station: In the main station, the works for the concreting of the platform slabs were completed, while in progress are the works for reinforcing the foundation slab of the main entrance (-2.00).
    In the underground section of the station: Phase A and B’ excavation works (top and bench) (progress: 46.545m/46.545m) are in progress.
    At the entrance of Korai square: the works for the installation of a temporary retaining system (shotcrete, pre-stressed anchors, struts) up to the final excavation bottom were completed.
    At the entrance of P. Bakoyianni square: the works for the installation of a temporary retaining system (shotcrete, pre-stressed anchors, struts) up to the level of the 1st phase are in progress.
    At Dimotiko Theatro ventilation shaft: the construction of temporary retaining piles – 32 pieces/43 pieces – is in progress.
    In the NATM triple track tunnel towards the University of Piraeus, the Phase A excavation works (excavation progress: 95.61m./140m.) and the Phase B excavation works (excavation progress: 89.61m/140m.) are in progress.
    In the NATM triple track tunnel towards DIMOTIKO THEATRO, Phases A and B (TOP) excavation works were completed (63m./63m.), Phase C excavation works (BENCH) (9m./63m) are in progress.
    In the TBM double track tunnel, the construction of the 4th Interstation is in progress.
    The tunnel excavation has been completed by 54%.