Piraeus

Piraeus

On November 21st 2008 ATTIKO METRO S.A. proceeded to the re-procurement of the project related to Line 3 Metro extension to the Western Suburbs, terminating in the area of Piraeus (underground tunnel, 7.6 km long, with 6 modern stations: Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus, Dimotiko Theatro).

On February 13th 2009, 6 technical consortia/joint ventures expressed their interest in the construction of the project. On October 5th 2011, ATTIKO METRO S.A. proceeded to the unsealing of the Financial Offers for the Project concerning the extension of Metro Line 3 to Piraeus.

The classification order of the three bidding joint ventures, based on their Financial Offer, is as follows:

JOINT VENTUREFINANCIAL OFFER
1. J&P – ΑVΑX ΑΕ – GHELLA SPA – ALSTOM TRANSPORT SA343.96 million €
2. AKTOR ΑΤΕ – ΤΕRΝΑ ΑΕ349.00 million €
3. FCC CONSTRUCCION S.A. – ALPINE BAU GMBH349.75 million €

Based on the aforementioned Tender results, J&P – ΑVΑX S.A. – GHELLA SPA – ALSTOM TRANSPORT SA is the lowest-bidder of the Tender.

On March 1st 2012, the relevant contract was signed with the contracting joint venture J&P – AVAX S.A., GHELLA SPA, ALSTROM TRANSPORT S.A for the construction of Line 3 extension from Aghia Marina to Piraeus, 7.6 km long in total, with 6 modern Metro Stations. Attiko Metro S.A. was represented by Mr. Christos Tsitouras, Chairman of the BoD and Managing Director, while the Construction Joint Venture J&P ΑVAX SA was represented by Mr. Konstantinos Mitzalis, Managing Director.

This Project constitutes a 730,000,000 EURO investment in areas of Piraeus Municipalities and other Municipalities in the wider area (Nikea, Korydallos, Aghia Varvara), which are currently faced with acute traffic problems and sub-standard services, in terms of Public Transport Modes.

The Metro Extension to Piraeus will serve approximately 132,000 passengers on a daily basis, while the distance between the Port and the International Airport will be covered by the Metro in just 45 minutes. Additionally, once the Metro becomes operational, the number of vehicles will be reduced by approximately 23,000 on a daily basis, leading to a respective daily reduction in CO2 by 120 tn.

Especially as regards Piraeus Station, a major Transportation Junction will emerge, connecting the two Metro Lines (Line 1 and Line 3), the Port, the Suburban Railway and the Tramway, which is also foreseen to pass through the same area, providing, thus, inter-modal transfers.

The Metro tunnel will be constructed using a Tunnel Boring Machine (TBM) in order to minimize the inevitable disturbance to the functions of the Municipalities; during the construction period (2012-2017) 2,000 persons in total are foreseen to be employed in this Project.

The extension of the Tramway from Neo Faliro to Piraeus centre recently commenced, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway network. More specifically, in January 2013 the contract was signed between ATTIKO METRO S.A. and the Company THEMELI S.A.

Apart from the Line 3 Extension to Piraeus, ATTIKO METRO S.A will shortly be engaged in the following projects as well, namely:

  1. Extension of the Tramway network from Neo Faliro to Piraeus centre, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway. The construction of this specific project commenced in September 2013 by ATTIKO METRO.
  2. Conversion of Line 1 (ISAP) section form N.Faliro to Piraeus into an underground structure, with the addition of one new station in the area of Keranis Factory, unifying, in terms of functions and town planning the areas of Piraeus currently served by the surface ISAP Line 1. The designs pertaining to this Project are about to be completed enabling, thus, ATTIKO METRO S.A. to put it to Tender.
  3. Extension to the Tramway Network to Keratsini – Perama, following an underground alignment at a large part of Keratsini Municipality, running along the alignment of the old Perama tramway. The Advanced Concept Designs regarding this Project are underway.
LINE 3 EXTENSION TO PIRAEUS
Location of the Stations

Aghia VarvaraEleftheriou Venizelou Av. (Ag. Eleoussa)
KorydallosEleftherias Square
NikaiaEl.Venizelou Square
ManiatikaEtolikou & Mavromihali Str.
PiraeusPort (close to ISAP station)
Dimotiko TheatroIroon Polytechniou & Vassileos Georgiou

Tunnel

6,5km of the tunnel of the extension will be constructed using the Tunnel Boring Machine, while the remaining parts at the beginning and at the end of the project will be constructed via the underground excavation method.

Shafts

8 ventilation shafts in total shall be constructed along the new Line and two shafts for the TBM’s entering/exiting.

PROGRESS OF WORKS

October 2016

  • NIKEA Station: The works for the construction of industrial floors at the concourse level of the Station are in progress. In addition, in progress is the construction of the permanent lining of the main station (phase B’): construction of exterior perimeter walls at the E/M level of the floor slab up to the roof slab level, at the perimeter of axes B-D and 14-15, as well as construction of perimeter parapet walls above the roof slab of the main station.
  • At the northern entrance, the works for the construction of the permanent lining of the C/C of the station entrances are in progress, with the installation of steel reinforcement for the construction of exterior perimeter walls at access 3.
  • MANIATIKA Station: The archaeological excavation has been completed. In progress are excavation works and works for the temporary retaining of the 14th level (area where deepening works are under execution) of the main building of the Station.
    At the main tunnel of the Station, the excavation and temporary retaining works have been completed, while in progress are the excavation and temporary retaining works of the transverse horizontal sections of the access galleries of the main tunnel and the bottom transverse access gallery to the lifts.
    At the emergency exit on Gythiou street, as well as at the southern ventilation shaft of the Station, worksite occupation and fencing works have been completed.
  • DIMOTIKO THEATRO Station: In progress are formwork, reinforcement and concreting works of parapet walls and columns from the E/M level (-1) up to the roof level.
    At the underground section of the Station, in progress are the vault concreting works (progress of works 12/46m).
    At the entrances on Korai and Bakogianni squares, respectively, excavation and temporary retaining works have been completed up to the final level.
    At Dimotiko Theatro ventilation shaft, the construction of the temporary retaining up to the 3rd row of struts has been completed.
    In the NATM triple track tunnel towards the University of Piraeus, Phase C’ excavation works (BENCH) (excavation progress: 128.61/140m.) are in progress.
    The excavation of all tunnels has been completed by 61.50%.
Print Friendly, PDF & Email

September 2016

  • Komninou Shaft: The works for the worksite installations have been completed. Excavation and temporary retaining works are in progress.
  • AGHIA VARVARA Station: Backfilling works are in progress.
    At Taxiarchon Shaft, the construction and concreting of the foundation slab are completed.
  • KORYDALLOS Station: Filling works and works related to industrial and other special flooring are in progress.
  • NIKEA Station: The works for the construction of non-bearing inner masonry walls, the masonry plastering works at E/M level, the works for the construction of machinery footings in technical rooms 3.1.3, 3.1.4, 3.1-1, 3.11a-1 at the E/M slab and the concourse level slab are completed. Completed are also the waterproofing and the construction of the permanent lining of the station NATM tunnel.
    In progress are masonry plastering works at the concourse slab and at the station north platform slab, painting preparation works at the E/M level and works for the construction of machinery footings in technical room 3.7-2 at the concourse level. At the northern entrance, the works for the waterproofing of the foundation slab are completed. In progress are works for the construction of the permanent lining of a section of the foundation slab of the C/C entrances in the area on either side of piles P 136-111 and P 163-157 (access 3), P 125-128 & P 163-168 (access 2).
  • MANIATIKA Station: Excavation and temporary retaining works for the transverse horizontal sections of the access tunnels of the station main tunnel are in progress.
  • PIRAEUS Station: At Roloi Shaft, in progress are works for expanding the worksite fencing for the construction of the sewage network diversion.
  • DIMOTIKO THEATRO Station: In the underground section of the station, vault reinforcement installation works are completed, while in progress are works for the assembly of the steelwork for vault concreting.
    At Dimotiko Theatro Ventilation Shaft, construction works for the temporary retaining up to the 2nd row of struts are completed while the works for the excavation and temporary retaining up to the 3rd row of struts are in progress
    In the NATM triple track tunnel towards the University of Piraeus, Phase D’ excavation works (INVERT) are in progress (excavation progress: 20/140m.).
    In the NATM triple track tunnel towards DIMOTIKO THEATRO, Phase D’ excavation works (INVERT) are completed (excavation progress: 63/63m).
    At Deligianni Shaft, the works for the excavation and temporary retaining of the final level are completed.
    At Panepistimio Shaft, the works for the diversion of the water supply network are in progress.
    The tunnel excavation has been completed by 59.70%.