Project progress

Project progress

The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

PROGRESS OF WORKS

August 2016

  • NEW RAILWAY Station: The works for the construction of retaining piles in the shafts and the diversion of the combined-flow network are in progress.
  • DIMOKRATIAS Station: the excavation works are completed, while in progress are the preparatory works for the subsequent traffic phase.
  • AGHIA SOFIA Station: The works for the construction of the northern access (anchors, struts) are in progress.
  • SINTRIVANI Station – REPORT: The works for the construction of the foundation micro-piles, along with the excavation and temporary retaining of the northern access are completed. In progress are the preparatory works for the subsequent traffic phase along with the archaeological excavations at the southern ventilation shaft.
  • PANEPISTIMIO Station: In progress are the works for the construction of the platform.
  • PAPAFI Station: In progress are the works for the construction of the slab at -2.
  • EFKLEIDIS Station: In progress are the works for the construction of the pits for the E/M routing.
  • FLEMING Station: In progress is the construction of foundation slab.
  • TBM tunnels: In progress is the construction of the TBM tunnel from Voulgari Station to Patrikiou Crossover.
  • ANALIPSI Station and Crossover: In progress are preparation works for the arrival of the two TBMs at the crossover.
  • Cut and Cover Tunnel: Section III: Temporary retaining works are in progress. Moreover, PUO network diversions in its section at Allatini Street are in progress.
Print Friendly, PDF & Email

June 2016

  • Dimokratias Crossover: Works for the excavation of the final level are in progress.
  • DIMOKRATIAS Station: Completion of the construction of slab -2. Moreover, in progress is the archaeological excavation of the final level.
  • SINTRIVANI Station – REPORT: In progress is the temporary retaining of the northern access.
  • PAPAFI Station: In progress are the works for the construction of the invert slab and the waterproofing of the walls above the invert slab.
  • FLEMING Station: In progress is the construction of foundation micropiles.
  • ANALIPSI Station and Crossover: In progress are preparation works for the arrival of the two TBMs at the crossover.
  • DEPOT: At building complex I, in progress is the construction of the bearing structure and the masonry walls at level -2. At building complex II, in progress is the construction of the bearing structure of building 6.
  • Cut and Cover Tunnel: Excavation works and temporary retaining works are in progress.
Print Friendly, PDF & Email