Project progress

Project progress

The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

PROGRESS OF WORKS

February 2016

  • Dimokratias Crossover: The works for the construction of level -2 were completed, while the preparation for the excavation of level -3 is in progress.
  • DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress.
  • SINTRIVANI Station: Preparatory works for the excavation of level -4 are in progress.
  • PANEPISTIMIO Station: Civil Works were completed.
  • PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls and for the construction of piles at the eastern access are in progress.
  • DEPOT: At the building complex II, the works for the construction of building 9 and the foundation of the Operations Control Centre (OCC) continue.
  • In progress is the TBM installation at NEA ELVETIA Station for the construction of the remaining Nea Elvetia – Analipsi tunnel section. Moreover, in progress is the construction of retaining piles at the C/C tunnel.
Print Friendly, PDF & Email

January 2016

  • PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls are in progress.
  • VOULGARI Station: The works for the POY network diversions, traffic arrangements and worksite installations are in progress.
  • NEA ELVETIA Station & Crossover: At the crossover, the construction of the foundation slab is completed, while the works for the assembly of the TBM are in progress.
  • DEPOT: At the building complex I, the works for the construction of the ground floor slab are in progress, while at the building complex II, general excavation works and the works for the construction of the roof of the slab and the walls of building 7 continue.
  • The works for the excavation and the temporary retaining of the C/C tunnel are in progress.
Print Friendly, PDF & Email