Project progress

Project progress

The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

PROGRESS OF WORKS

December 2016

• Dimokratias Crossover: Works for the construction of the foundation slab at the northern part have been completed.

• SINTRIVANI Crossover: Works for the concreting of provisional openings are in progress.

• PANEPISTIMIO Station: Works for the construction of masonry walls at level -1 have commenced.

• PAPAFI Station: Works for the construction of the roof slab are in progress.

• ANALIPSI Station and Crossover: Preparation works have been completed for the TBM2 arrival at the crossover, while in progress are works for the implementation of the next traffic phase.

• PATRIKIOU Station and Crossover: The construction of the roof slab at the Crossover, as well as the excavation at level -1 of the station have been completed, while in progress is the construction of the level -1 slab of the station.

• VOULGARI Station: Excavation works at level -1 have been completed, while the construction of the level -1 slab is in progress.

• TBM Tunnels: Works for the boring of the twin tunnels from NEA ELVETIA Station to PATRIKIOU Station have been completed. Works for the boring of TBM2 tunnel extending from PATRIKIOU Station to ANALIPSI Station are in progress.

• Cut and Cover Tunnel – Section I: In progress are works for the construction of the tunnel invert.

Print Friendly, PDF & Email

November 2016

  • NEOS SIDIRODROMIKOS STATHMOS Station: In progress are masonry works at level -1.
  • Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while works for the construction of the foundation slab are in progress at the northern part.
  • DIMOKRATIAS Station: In progress is the archaeological excavation at the northern access and at the northwest shaft.
  • SINTRIVANI Station – Thessaloniki International Fair: Piling works have been completed at the southern access. In progress is the construction of the northern access, as well as the northern shaft walls and the archaeological excavation at the southern access.
  • SINTRIVANI Crossover: In progress are works for the closing of provisional openings of the slabs.
  • PANEPISTIMIO Station: Civil works have been completed.
  • PAPAFI Station: The construction of walls at level -2 and the slab of level -1 have been completed. In progress is the construction of walls at level -1, and the works at the northern ventilation shaft, as well as the works for the construction of the northern access.
  • FLEMING Station: Preliminary works for the next traffic phase.
  • ANALIPSI Station and Crossover: The works for the closing of openings at the slabs at the northern access were completed.
  • PATRIKIOU Station and Crossover: The construction of the roof slab at the Crossover, as well as the retaining piles at the eastern ventilation shaft and the excavation at level -1.
  • VOULGARI Station: The construction of the roof slab has been completed. Excavation works at level -1 are in progress.
  • NEA ELVETIA Station and Crossover: Excavation and temporary retaining works (construction of 5th -6th series of anchors) are in progress at a minor section of the station. Waterproofing works at a section of the foundation slab are also in progress.
  • DEPOT: Building complex I: The reinforced concrete bearing structure has been completed. Masonry works are being constructed at level +1. Building complex II: The construction of retaining walls in the surrounding area is in progress.
  • TBM Tunnels: Works for the boring of TBM2 tunnel at the section extending from Voulgari Station up to Patrikiou Crossover have been completed. Works for the boring of TBM1 tunnel extending from Voulgari Station up to Patrikiou Crossover are in progress, while in progress is also the jet grouting construction process in Patrikiou – Analipsi interstation.
  • Cut and Cover Tunnel – Section I: In progress are waterproofing works in a section of the tunnel invert. Section III: Excavation and temporary retaining works of the NATM tunnel are in progress.