Day: June 11, 2014

May 2014

KORYDALLOS Station: The works for the general excavation of the Station and the works for the improvement of the foundation invert – placement of a drainage layer have been completed. Waterproofing works, the works for the placement of reinforcement and foundation slab concreting works are in progress. NIKEA Station: Excavation…
Μάθε Περισσότερα

May 2014

NEW RAILWAY Station: Civil works were completed. AGHIA SOFIA Station: The archaeological excavation at the southern part of the station is in progress. SINTRIVANI Station: Excavation works at level 3, as well as the works for the construction of a NATM ventilation tunnel, are in progress. PAPAFI Station: Excavation works…
Μάθε Περισσότερα

May 2014

Traffic arrangements were completed at the current phase in the Central district and district A’ of Piraeus Municipality; The urban planning works at the sidewalk of Grigoriou Lambraki street are in progress; The technical works at various locations of the Tramway route (at Peace and Friendship (SEF) terminal Tramway stop,…
Μάθε Περισσότερα

May 2014

TBM Start-up Shaft, Micra: The works for the construction of piles and cap beams are in progress. Topographic works at various locations of Kalamaria Extension Project, as well as the preparation, review and approval of the designs for the relocation and diversion of PUO networks, the designs for traffic arrangements-diversions,…
Μάθε Περισσότερα