Day: July 10, 2014

June 2014

NIKEA Station: The excavation and muck disposal, as well as the construction of the temporary retaining (shotcrete, prestressed anchors, metal struts) at levels 5 and 6 of the main Station were completed. The excavation and disposal of excavation spoils of the main Station (levels 7, 8 and final excavation level),…
Μάθε Περισσότερα

June 2014

DIMOCRATIAS Station: The construction of conventional parapet walls southwards is in progress; SINTRIVANI Station: The excavation works at level 2 were completed, while the construction of slab at level 3, the construction of NATM ventilation tunnel and the archaeological excavation works at the northern access are in progress; PANEPISTIMIO Station:…
Μάθε Περισσότερα

June 2014

The works for the relocation of Trolleybus line No. 20 have commenced (from Vas. Georgiou street to Bouboulinas street); The works for the relocation of PUO networks (i.e. of the sewage pipe at Grigoriou Lambraki street) and of PPC networks at SEF (Piece and Friendship Stadium) stop area and at…