NEW RAILWAY Station: The construction of the NW & NE shaft, as well as the restoration of openings (level 1) at the crossover, are in progress; DIMOKRATIAS Station: The construction of the southern part of the roof slab was completed; PANEPISTIMIO Station: The excavation of level 4 has commenced; PAPAFI…
Μάθε Περισσότερα

July 2014

AGHIA VARVARA Station: The works for the construction of the platform columns and floor slab are currently in progress; KOLYDALLOS Station: Completion of the works related to the drilling, embedding and tensioning of the pres-stressed anchors, as well as of the Station’s raft concreting works; NIKEA Station: In progress are…
Μάθε Περισσότερα

July 2014

Technical works are currently in progress at various locations along the tramway route. More specifically, the construction of the foundation piles for Myrtidiotissa Bridge at SEF terminal Stop has been completed, while other works are currently in progress. Moreover excavations in the area of Lambraki reversing point have been completed,…
Μάθε Περισσότερα

July 2014

The works for the construction of piles for peripheral retaining, as well as excavation works at NEA KRINI Station have commenced; The preparation, review and approval of the designs for the relocation and diversion of PUO networks, the traffic arrangements-diversions and the final designs of the stations are at an…
Μάθε Περισσότερα