AGHIA VARVARA Station: The works for the removal of precast segments of the false tunnel are in progress; MANIATIKA Station: In progress are the excavation and temporary retaining works of phase A1 (south front – eastern gallery and north front – western gallery) of the station’s main tunnel. In progress…
Μάθε Περισσότερα

October 2015

In progress are the relocations of the following PUO networks: sewage and EPA at Vassileos Georgiou, EYDAP (water supply and sewage) networks at the sidewalk adjacent to Grigoriou Lambraki street, sewage and EPA networks at Omiridou Skylitsi street, OTE & fiber optics at Ethn. Antistaseos street & street lighting at…
Μάθε Περισσότερα

October 2015

NOMARCHIA Station: Works for the phase A excavation, the construction of struts at level -1 and the perimeter piles cap beam are in progress; NOMARCHIA Crossover: Works for the construction of perimeter retaining piles and their cap beam, as well as works for the diversion of PUO networks are in…