AGHIA VARVARA Station: The works for the waterproofing, construction of walls and platform floors, of perimeter walls up to the ticket issuing level, as well as the works for the construction of walls up to the roof level are in progress. Taxiarhon Shaft: The excavation works along with the works…
Μάθε Περισσότερα

January 2016

Completed are the relocations of sewage, PPC & and EPA networks at the sidewalk adjacent to Grigoriou Lambraki street, Sewage, EPA & Fiber Optics at Vassileos Georgio street and the ILPAP abolished lines dismantling works at Vassileos Georgiou street. In progress are the relocations of the water supply networks at…
Μάθε Περισσότερα

January 2016

PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls are in progress. VOULGARI Station: The works for the POY network diversions, traffic arrangements and worksite installations are in progress. NEA ELVETIA Station & Crossover: At the crossover, the construction of the foundation slab is completed, while the…
Μάθε Περισσότερα

January 2016

NOMARCHIA Station: The excavation of the station’s level -1 is completed, while the works for the installation of metal struts at level -1 are in progress. NOMARCHIA Crossover: The excavation of the crossover’s level -1 is completed, while the works for the installation of metal struts at level -1 are…