Day: December 19, 2016

November 2016

NOMARCHIA Station: The construction of the permanent lining from the foundation slab up to level -2 is in progress. NOMARCHIA Crossover: The construction of the permanent lining from the foundation slab up to level -1 was completed. In progress is the construction of the slab of level -1 and the…
Μάθε Περισσότερα

November 2016

NEOS SIDIRODROMIKOS STATHMOS Station: In progress are masonry works at level -1. Dimokratias Crossover: Works for the construction of the northern part foundation micro-piles have been completed, while works for the construction of the foundation slab are in progress at the northern part. DIMOKRATIAS Station: In progress is the archaeological…
Μάθε Περισσότερα

November 2016

• At Ethnarchou Makariou street, tramway construction works (earthworks and trackwork) are in progress from Zaimi area up to Papandreou Bridge. • At Mikras Asias street, urban planning works were completed through the execution of planting works, while the works for the construction of the Tramway at the pocket area…
Μάθε Περισσότερα

November 2016

At the beginning of the extension, in the double track NATM tunnel, Phase A tunnel excavation works from the TBM shaft to Aghia Marina have been completed. Phase B and C tunnel excavation works are in progress. KORYDALLOS Station: Painting works are in progress. NIKEA Station: Painting works are in…
Μάθε Περισσότερα