December 2015

  • AGHIA VARVARA Station: The works for the removal of the pseudo-tunnel and the last ring’s precast segments are in progress;
  • NIKEA Station: The works for the installation of the station’s escalators from the concourse to the platform level are in progress;
  • MANIATIKA Station: The excavation and temporary retaining works of phase A1 (eastern gallery) and phase A2 of the southern front of the station’s main tunnel are in progress;
  • PIRAEUS Station: The preparation works for the construction of diaphragm walls is in progress.
    The archaeological excavation works are in progress in the Shaft;
  • DIMOTIKO THEATRO Station: The Phase A excavation works (top and bench) – (excavation progress: 8.87m/46.545m), as well as the Phase B excavation works (top and bench) – (excavation progress: 2.77m/46.545m) are in progress.
    The works for the TBM maintenance and the partial relocation of the TBM worksite are in progress.
    In the NATM triple track tunnel towards the University of Piraeus, the Phase A excavation works (excavation progress: 44.61m/140m.) and the Phase B excavation works (excavation progress: 44.61m/140m.) are in progress.
    In the NATM triple track tunnel towards DIMOTIKO THEATRO, the Phase A excavation works (excavation progress: 34.82m/63m.) and the Phase B excavation works (excavation progress: 34.82m/63m) are in progress. Moreover, the construction of the 5th row of forepoles are in progress.
    At Panepistimio shaft, the archaeological investigation in the PUO network diversion areas is in progress.
    The tunnel excavation has been completed by 50.547%.