Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • AGHIA VARVARA Station: The works for the construction of the platform columns and floor slab are currently in progress;
  • KOLYDALLOS Station: Completion of the works related to the drilling, embedding and tensioning of the pres-stressed anchors, as well as of the Station’s raft concreting works;
  • NIKEA Station: In progress are the works for the construction of the Foundation Earthing, as well as for the temporary drainage of the floor of the final excavation level of the main Station’s C/C part (axes 8-15);
  • MANIATIKA Station: Completion of the pile cap beam construction works – In progress are the works for the excavation of the 7th and 8th levels, the application of the shotecrete and the construction of the pre-stressed anchors at level 7 of Station’s main structure;
  • PIRAEUS Station: Completion of the drilling operations for the construction of a water-jet drilling, the installation of piezometers and trial pumping at access 3, as well as the works for the demolition of three small buildings. The works for dismantling gates E5 and E6 are also completed. Still in progress are the works for the construction of the natural gas pipe networks at the location where PUO diversion works are executed. Moreover, in the framework of the traffic arrangement, completion of the construction of the industrial floor and the water supply manholes in view of changing the ships mooring location, the arrangement of EYDAP’s pumping station corridor and the configuration of the surrounding area, the construction of new walkways in the area of Gate E7 and the relocation of OLP’s lighting pole; at the same time, in progress are the works for the construction of the stormwater drainage network, the construction of traffic lights network, the construction of ILPAP network and the construction of the street lights;
  • DIMOTIKO THEATRO Station: Completion of the works for the construction of piles and pile cap beams at Aghiou Konstantinou square, as well as of the works for the construction of the temporary retaining piles at Korai Square;
  • Completion of EYDAP network diversion works at Deligianni Shaft; completion of dismantling/removal works in the section located inside the yard area of the University at Panepistimio Shaft; archaeological excavations in this area are in progress;
  • Commencement of the tunnel boring operations for the 2nd interstation; 12% completed so far.
Print Friendly, PDF & Email
WCAG