Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

March 2013

  • The works for the construction of temporary retaining piles and the pile cap beam at the TBM start-up shaft have been completed;
  • The works for the dismantling of shop sheds, as well as for the construction of new sidewalks at the eastern and southern part of Eleftherias square at KORYDALLOS Station, have been completed;
  • The works for the diversion of PPC and OTE networks, as well as the traffic arrangements at El. Venizelou street at AGHIA VARVARA Station, have been completed.
Print Friendly, PDF & Email
WCAG