  • New Railway Station: The works for the construction of a northern-west and northern-east manhole and the reinstatement of openings at level 1 of the crossover are in progress;
  • AGHIA SOFIA Station: The archaeological excavation at the southern section of the Station is in progress;
  • SINTRIVANI Station: The works for the excavation and the construction of level 3 slab are at an advanced stage. Traffic phase A works have been implemented and completed;
  • PANEPISTIMIO Station: Excavation works at level 4 are in progress;
  • PAPAFI Station: Excavation works for level 3 (platform) are at an advanced stage. The works for the installation of the struts at level 4 have been completed, while the construction of the western access has commenced;
  • ANALIPSI Station and Crossover: The works for the excavation and construction of the slab at level 3, the construction of ventilation shafts 1, 2 & 3 and of the eastern access are at an advanced stage;
  • PATRIKIOU Station and Crossover: The construction of piles for the west manhole of the sewage duct has commenced;
  • VOULGARI Station: The works for the diversion of PUO networks are at an advanced stage;
  • NEA ELVETIA Station and Crossover: The works for the construction of the foundation slab at the crossover are in progress;
  • The works for staging the two TBMs at NEA ELVETIA Crossover are at an advanced stage, while piling works at the C/C tunnel are in progress.