August 2013

  • The concreting works of the slab at -1 level at DIMOKRATIAS Station are in progress.
  • The works for changing the traffic arrangements in AGHIA SOFIA Station are at the completion stage.
  • The roof slab backfilling works are in progress, while the excavation at the north-western shaft at SINTRIVANI Station is completed.
  • The works for the construction of diaphragm walls and the construction of bored-piles at PAPAFI Station are in progress.