  • The excavation works at the New Railway Station were completed, while the worksite area of the Forestation was released and reinstated.
  • The works for the construction of the slab at level -1 in DIMOKRATIAS Junction area were completed.
  • The works for the backfilling of the roof slab of the north section and the construction of EYATH duct at the northern section of AGHIA SOFIA Station, along with the construction of the retaining walls are in progress.
  • The construction of the roof slab was completed, while the works for the construction of forepoling in the micro-tunnels at SINTRIVANI Station are in progress.
  • The works for the construction of the Diaphragm Walls and the shaft piles at PAPAFI Station are in progress.
  • The installation of escalators at level -2 in EFKLIDIS Station is in progress.