  • Until the present day, seventy-four per cent (74%) of the archaeological excavations has been carried out and by the end of 2012 all excavation works are expected to be completed. During the archaeological survey, more than 10,000 finds have been revealed, especially along Egnatia Odos. At the current phase, archaeological excavations are being carried out at three locations of the Project: DIMOKRATIAS, VENIZELOU & AGHIA SOFIA Stations.
  • The two “Metromoles” have already bored over seventy-three per cent (73%) of the Metro tunnels, i.e. 12km of single track tunnel in total.
  • At EFKLIDIS Station, the first constructed station of Thessaloniki Metro Project, the works related to architectural finishes, as well as the installation of the E/M equipment, have commenced.