December 2009

  • The second Tunnel Boring Machine (ΤΒΜ2) continues its underground trip, thus having constructed 2,485m of parallel tunnel, while at the first Tunnel Boring Machine (TBM1) works related to the maintenance of the TBM’s cutterhead are executed.
  • Works related to construction of the metal bridge at DEMOKRATIAS Station commenced.
  • The archaeological excavation survey at the following locations of the project is in progress: NEOS SIDIRODROMIKOS STATHMOS, DEMOKRATIAS STATION, VENIZELOU STATION, SINTRIVANI STATION.