Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

September 2009

  • The first TBM (TBM1) has constructed 2300m of tunnel, while the second (TBM2) has constructed 1350m. of parallel tunnel.
  • The construction of diaphragm walls at PANEPISTIMIO and EFKLIDIS Stations is in progress, while the respective works at FLEMING Station commenced.
  • Works related to the construction of the metal bridge at VENIZELOU and AGHIA SOFIA Stations are in progress.
  • Works related to PUO network at the eastern section of the project are at a final stage. The surface worksite area will be reduced soon and the construction works will be executed below surface.
Print Friendly, PDF & Email
WCAG