Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • The assembly of the first Tunnel Boring Machine is at a completion phase.
  • The construction of diaphragm walls at Syntrivani will be completed soon (currently completed at a percentage of 86%).
  • In the area where the orphanage “Alexander the Great” was located, excavation works commenced for the construction of a building at the expense of AM where the 1st Laboratory of Special Professional Training in Thessaloniki will be housed.
  • Works related to the reinstatement of “Phoenix” Baths, which serves as the area where the archaeological finds of the 9th Byzantine Antiquities Department are stored, preserved and safeguarded, were completed.
Print Friendly, PDF & Email
WCAG