December 2007

  • The construction of the diaphragm walls on the northern side of VENIZELOU Station was completed and early next year relevant works will commence to be executed on the southern side of the Station.
  • The construction of diaphragm walls commenced at the Branching of the extension to Stavroupoli in the area of DEMOKRATIAS Station.
  • PUO network diversions were completed at 7 worksite areas.
  • Nine (9) worksites have been occupied until the present day and two additional worksites will be installed soon.