Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
  • NOMARCHIA Station: The excavation of level -3 of the station, as well as the works for the installation of metal struts at the 3rd level have been completed. In progress are the excavation and temporary retaining works up to the invert.
  • NOMARCHIA Crossover: The excavation works of level -3 have been completed, while the works for the installation of metal struts at level -3 are in progress.
  • KALAMARIA Station: The excavation works at level -1 of the station and the installation of metal struts at the 1st level have been completed. In progress are the excavation works at level -2.
  • NEA KRINI Station: The works for the construction of the roof slab and the walls at the roof level have been completed. In progress are the waterproofing works of the Station, as well as the excavation-retaining works at the northern lateral extension of the Station.
  • MIKRA Station & Crossover: The excavation and temporary retaining works are in progress.
  • The preparation and approval of designs are in progress.
Print Friendly, PDF & Email
WCAG