February 2016

  • NOMARCHIA Station: The works for the installation of metal struts at level -1 were completed, while the excavation of the station’s level -2 is in progress.
  • NOMARCHIA Crossover: The works for the installation of metal struts at level -1 are in progress.
  • KALAMARIA Station: Works for traffic arrangements – Phase D – were completed. At the western section, in progress are the works for the construction of the perimeter piles cap beam and for the construction of reinforced concrete struts.
  • ARETSOU Station: Works for the relocation of EYATH and OTE networks were completed. In progress are the works for the implementation of traffic arrangements – phase A – and for the construction of prestressed anchors for temporary retaining.
  • NEA KRINI Station: Works for the construction of the slab at level -1 were completed. Works for the construction of walls up to the roof slab, the construction of a fire fighting tank and for the installation of the station’s waterproofing system are in progress.
  • MIKRA Station: Works for the construction of the piles for the temporary retaining of the staircase were completed.
  • MIKRA 2nd Crossover: Works for the construction of perimeter piles’ cap beam, as well as preparatory works for the installation of struts at the roof level are in progress.
  • MIKRA Forestation: Works for the construction of perimeter retaining piles, the configuration of the worksite area, the diversion of PUO networks, as well as preparatory works for traffic arrangement – phase A – are in progress.
  • Kritis shaft: The construction of the 2nd level metal struts is completed.
  • The expropriation of areas in ARETSOU, MIKRA (part) Stations and MIKRA Forestation has been completed, while the supplementary expropriation of an area in a small part of MIKRA Station is still pending.