Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

December 2015

  • In progress are the relocations of the following PUO networks: EYDAP (water supply and sewage) networks – PPC & and EPA at the sidewalk adjacent to Grigoriou Lambraki street, Sewage – EPA & Fiber Optics at Vassileos Georgiou, EPA at Akti Possidonos, OTE & Fiber Optics at Ethn. Antistaseos street, Sewage &- EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street;
  • The archaeological excavation at the PUO relocation trenches on Grigoriou Lambraki and Vassileos Georgiou streets is in progress;
  • Trackwork construction works are in progress at Papandreou and Lambraki Bridges, on M. Asias Street and on Lambraki Street reversing. Trackwork construction works have commenced and are in progress at Grigoriou Lambraki Street. Works are in progress for the construction of Tramway stops on Mikras Asias street and at Gr. Lambraki bridge. Catenary poles foundation works are in progress on Grigoriou Lambraki, Ethnikis Antistaseos and Vassileos Grigoriou Streets. Works at Lambraki pedestrian bridge are in progress along with the works for the connection of the pedestrian passage at Karaiskaki stop to the existing underground passage;
  • The urban planning work at the sidewalk adjacent to Mikras Asia, on Lambraki Street reversing, at the sidewalk adjacent to Ethinikis Antistasseos Street at the opposite sidewalk at Vassileos Georgiou Street are in progress.
Print Friendly, PDF & Email
WCAG