November 2015

  • In progress are the relocations of the following PUO networks: EYDAP (water supply and sewage) networks – PPC & and EPA at the sidewalk adjacent to Grigoriou Lambraki street, Sewage – EPA & Fiber Optics at Vassileos Georgiou, EPA at Akti Possidonos, OTE & Fiber Optics at Ethn. Antistaseos street, Sewage &- EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street.
  • The works for the dismantling of abolished trolley-bus networks at Vas. Georgiou & Ethn. Antistaseos streets have been completed.
  • The archaeological excavation at the PUO relocation trenches on Grigoriou Lambraki and Vassileos Georgiou streets is in progress.
  • Trackwork construction works are in progress at Papandreou Bridge and on M. Asias Street, on Lambraki Street reversing and at Lambraki bridge.
  • Works have commenced and are in progress for the construction of Tramway stops on Mikras Asias street and at Gr. Lambraki bridge. Catenary poles foundation works have commenced and are in progress on Grigoriou Lambraki, Ethnikis Antistaseos and Vassileos Grigoriou Streets.
  • Catenary poles foundation works on Mikras Asias street and on Lambraki Street reversing have been completed.
  • The urban planning work at the sidewalk adjacent to Mikras Asia, on Lambraki Street reversing and Lambraki Bridge are in progress.
  • The works at the sidewalk adjacent to Ethnikis Antistasseos Street and at the opposite sidewalk at Vassileos Georgiou Street have commenced and are in progress.
  • The works for the configuration of Akti Moutsopoulou and Zanni intersection, the configuration works at the sidewalk adjacent to Grigoriou Lambraki Street (between Bouboulinas and Vassileos Georgiou Streets) and the works for the installation of underground waste bins and the relevant urban planning at 34thSyntagmatos Street have been completed.
  • The works for the installation of underground waste bins at Nikita Street is at the completion stage.