  • The works for the relocation of the sewage network located at the adjacent sidewalk of M. Asias Street have been completed. Works for the relocation of sewage and natural gas networks in Vas. Georgiou Street have commenced and are in progress. The works for the relocation of EYDAP sewage & water supply, EPA and OTE networks at G. Lambraki sidewalk adjacent to the tramway corridor are in progress. In progress are also works for the relocation of EYDAP network at Omiridou Skylitsi Street sidewalk adjacent to the tramway corridor (Ippodamias Square – 34th Syntagmatos Street), as well as works for the relocation of a stormwater network in Mikras Asias Street;
  • Construction works (foundation piling) for the pedestrian bridge at Lambraki Bridge are in progress, as well as technical works in the area where KARAISKAKI stop is foreseen to be located, at Lambraki Street reversing point, etc.;
  • Earthing works for the tramway corridor at Mikras Asias and Gr. Lambraki Streets are in progress. In progress are also the execution of investigation trenches for the catenary poles, as well as the manufacturing of the prefabricated trackwork slab;
  • Works for the configuration of Lambraki bridge sidewalks, Lambraki Street reversing point, Ethnikis Antistasseos sidewalk (across the Tramway corridor), Mikras Asias sidewalk adjacent to the tramway corridor, the area underneath Papandreou bridge, Alikakou Square, the junction of Bouboulinas and Grigoriou Lambraki Street (Kanari Square) etc. are in progress.