September 2016

  • At Ethnarchou Makariou Street, in progress are works for the relocation of the rainwater drainage pipe.
  • At Mikras Asias street, completed are the works for the construction of the tramway corridor from Papandreou Bridge past Sarantaporou Street. The urban planning of the area and Mikras Asias stop is completed.
  • At Grigoriou Lambraki street, the urban planning of the opposite sidewalk has been completed. Moreover, the construction of the tramway corridor and the urban planning works of the adjacent sidewalk (including Lambraki and Evangelistrias stops) from the U-turn in Lambraki Street up to Venizelou Street are in progress. In progress are also works for the construction of a tramway corridor from Venizelou Street up to Vas. Georgiou Street, as well as the urban planning of the adjacent sidewalk in this area.
  • At Vas. Georgiou street, the urban planning works at the opposite sidewalk and the works for the relocation of the rainwater drainage pipe at V. Georgiou and Ethn. Antistasseos junction have been completed, and in progress are the remaining works for PUO networks. In progress are the works for the construction of a tramway corridor and urban planning works from Lambraki up to Praxitelous Street. The archaeological excavations from Praxitelous to Iroon Polytechniou Street are in progress.
  • At Ethnikis Antistaseos street, completed are the urban planning works at the opposite sidewalk.
    In progress are works for the construction of the tramway corridor from Ippodameias street up to Tsamadou street, as well as the urban planning works at the adjacent sidewalk.
  • At Omiridou Skylitsi street, in progress are the works for the relocation of the PUO networks (from Lambraki Bridge to Tzavellas Street).
  • At Piece and Friendship Stadium (SEF) stop, works for the construction of the tramway corridor and reconfiguration of the stop are in progress.

(The reference “opposite” and “adjacent sidewalks” is related to the Tramway traffic).