Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

October 2016

  • NOMARCHIA Station: The waterproofing of masonry walls from the foundation slab to level -1 has been completed, while in progress is the construction of the platform.
  • NOMARCHIA Crossover: The waterproofing of masonry walls from the foundation slab to level -1 has been completed. In progress is the construction of scaffolding and formwork for the construction of the slab of level -1.
  • ARETSOU Station: The installation of 3rd level metal struts has been completed, while in progress is the excavation and temporary retaining up to the final level.
  • Pontou shaft: The excavation and installation of 1st level metal struts have been completed.
  • NEA KRINI Station: In progress is the construction of the walls.
  • 1st MIKRA Crossover: In progress is the excavation and temporary retaining down to the invert, as well as the waterproofing of the final level.
  • 2nd MIKRA Crossover: The excavation to the final level of anchors, as well as the construction of all anchors, except for the final one, have been completed.
  • MIKRA Forestation – Section 01: The installation of the 1st level struts and the excavation for the installation of the 2nd row of struts, as well as the construction of the 1st row of anchors, have been completed. Section 03 – 05: The construction of the 2nd row of anchors has been completed, while the construction of the 3rd row is in progress. Section 06-10: The excavation and shotcreting works to the final level have been completed.
  • The preparation and approval of designs are in progress.
Print Friendly, PDF & Email
WCAG