The most extensive transport project of Thessaloniki, a modern Metro network of high aesthetics, comes to life. More than 650 persons of various disciplines work on a daily basis for Thessaloniki Metro, while a total of 16 worksite areas have been developed throughout the city by the contracting Joint Venture.

Thessaloniki Metro, a 9.6 km network, shall have 13 modern stations, 18 fully automatic and air-conditioned trains, as well as platform screen doors in all stations, ensuring the provision of the optimum services to the passengers and their maximum safety. A 50,000 m2 depot is also foreseen in the area of Pylea.

It is worth pointing out that by incorporating state-of-the-art technical features in combination with the most stringent quality and operability standards, Thessaloniki Metro shall become the most advanced Metro network in Europe.

PROGRESS OF WORKS

April 2017

• NEW RAILWAY Station: The archaeological excavation at the south shafts is complete. The excavation and the temporary retaining of the southern shaft are in progress.

• DIMOKRATIAS Station: The construction of the temporary retaining at the southern access is in progress.

• SINTRIVANI Station – EXPO: The construction of masonry walls at level -1 is in progress.

• SINTRIVANI Crossover: The backfilling of the roof slab is in progress.

• PANEPISTIMIO Station: The reinstatement of the surface of the diaphragm walls is in progress.

• EFKLEIDIS Station: Plastering works at levels -1 and -2, doors installation and painting works at levels -1, -2 and -3 are in progress.

• FLEMING Station: The temporary retaining of the western access, the excavation and the temporary retaining of the northern and southern shaft and the construction of the masonry walls at levels -1 and -2 are in progress.

• PATRIKIOU Station and Crossing: Level -2 slab of the crossing has been completed. The excavation of level -3 of the station and the construction of the pile cap beam at the northeast shaft are in progress.

• VOULGARI Station: Excavation works at level -3 have been completed. The construction of level -3 slab and the excavation and temporary retaining of the eastern ventilation shaft are in progress.

• NEA ELVETIA Station and Crossover: The works for the construction of the platform have been completed. The construction of perimeter walls at level -1 of the station is in progress.

• Depot: At Building Complex II, the construction of the roof slab of the washing plant has been completed. The construction of tanks is in progress.

• TBM Tunnels: The dismantling of TBM 2 has been completed.

The dismantling of the networks in track 1 and the dismantling of TBM 1 are in progress.

• Cut and Cover Tunnel – Section I: The construction of the permanent lining is in progress. Section II: The excavation, retaining and construction of the permanent lining are in progress.

Print Friendly, PDF & Email

January 2017

• New Railway Station: In progress are the works for the repair of the surface of the diaphragm walls.

• Dimokratias Crossing: Works for the repair of the diaphragm walls surface are in progress.

• DIMOKRATIAS Station: In progress are the works for the excavation of the pumping station and the installation of struts at the northern shaft.

• SINTRIVANI Station – EXPO: In progress are works for the construction of the emergency exit and the platform staircases, the repair of the diaphragm walls surface and the works for the excavation and temporary retaining of the southern ventilation shaft.
• PANEPISTIMIO Station: In progress are works for the repair of the diaphragm walls surface.

• PAPAFI Station: In progress are works for the excavation of the western emergency exit and the preparatory works for the implementation of the next traffic arrangement.

• EFKLEIDIS Station: In progress is the construction of the masonry walls at level -1 and plastering works at level -3.

• FLEMING Station: The construction of the platform has been completed, traffic phase D’ has been implemented and in progress is the construction of piles for the temporary retaining of the western access.

• ANALIPSI Station and Crossover: Works for the implementation of the next traffic phase have been completed.

• PATRIKIOU Station and Crossing: The construction of the retaining piles of the shafts has been completed, while at the completion stage is the construction of the level -1 slab of the station.

• VOULGARI Station: Excavation works for level -2 are in progress.

• NEA ELVETIA Station and Crossover: In progress is the construction of the foundation slab of the Station.

• Depot: In progress is the construction of the foundation slab of the washing plant. At Building Complex I, in progress are preparatory painting works at levels -3 and -2. At Building Complex II, in progress is the construction of the bearing structure of section V, I as well as of the slab at level -1. In progress is also the construction of pile lining works at the southern section, while the archaeological works have been completed in the Depot access area.

• TBM Tunnels: Works for the boring of TBM2 tunnel extending from PATRIKIOU Station to ANALIPSI Station have been completed. In progress is the construction of the TBM1 tunnel within PATRIKIOU Station, at the direction to ANALIPSI Station.

• Cut and Cover Tunnel – Section I: In progress are works for the construction of walls, supporting columns and waterproofing. Section III: In progress are works for the implementation of the next traffic phase.