On February 20th 2006, the Contract was signed for further extending Line 3 by 1.5km and constructing one new Station in Haidari area and one depot in Eleonas area. Through this project, Line 3 of the Athens Metro is further extended to the western suburbs, thus reaching the areas of Haidari and to Aghia Varvara.
It is a very important project, given that it will serve the needs of the citizens of the western suburbs of Athens. Upon commissioning of the said extension, it will only take 9 minutes to reach the city centre (SYNTAGMA), while it will be possible to reach directly ELEFTHERIOS VENIZELOS Airport comfortably and in a safe and reliable manner in 40 minutes!
In particular, it is anticipated that this extension will contribute to the upgrading of the areas, which, until the present time, have not been within easy reach of the city centre, such as the wider area of Egaleo, Haidari and Aghia Varvara. It will also serve specific destinations such as the Hospital for Infectious Diseases, the 'Dromokaitio' Hospital, the Attiko Hospital and the commercial area.
It is estimated that AGHIA MARINA Station will serve over 30,000 new passengers on a daily basis.
The project related to EGALEO - AGHIA MARINA extension includes:
 |
The tunnel of the line, approximately 1,5 km long, which is to pass beneath Iera Odos and will be bored by means of the conventional underground method. |
|
 |
 |
AGHIA MARINA Station, in the building plot delimited by Iera Odos, Krinis, Katsarou and Aghias Marinas Streets, with two entrances/exits on either side of Iera Odos |
|
 |
 |
The Transfer Station which is constructed concurrently in the area where AGHIA MARINA Station is to be situated, with parking facility of 380 spaces. |
|
 |
 |
The Depot in the area of Eleonas, with a total surface of 86,000 m2, a Project to be described in detail here below.
|
PROGRESS OF WORKS
|
July 2011 |
|

| |
 |
The installation of granites tiles in the Station’s surrounding area is about to be completed. |
 |
The construction of sidewalks on Krinis and Agias Marinas Streets is at a completion stage. |
|
|
 |
|
June 2011 |
|

| |
 |
The works for the reinstatement of Aghia Marina and Krinis Streets are at an advanced stage; these streets formed previously part of the Metro worksite area. |
 |
The passenger information boards at the station platform level have been installed. |
|
|
 |
|
May 2011 |
|

| |
 |
The works related to architectural finishes at the Station entrances/exits are at the completion stage. |
 |
The works for the insulation of the roof in the car park area used for the transfer to the Metro network have been completed. |
|
|
 |
|
April 2011 |
|

| |
 |
The installation of stainless steel elements at the entrances/exits of the Station are at an advanced stage while the works for the installation of the glass panes at the sheds have been completed. |
 |
The works for the installation of the industrial floor at the Transfer Station have been completed. |
|
|
 |
|
March 2011 |
|

| |
 |
The works for the installation of the glass panels on the sheds of the station’s entrances/exits have commenced. |
 |
Plastering works are completed within the area of the illustrated private vehicle parking facility. |
|
|
 |
|
February 2011 |
|

| |
 |
The configuration of the Station entrances / exits has been completed. |
 |
The works for the planting of trees on the roof of Eleonas Depot buildings have commenced. |
|
|
 |
|
January 2011 |
|

| |
 |
Painting works have commenced at the 4-storey parking facility next to Haidari Metro Station. |
|
|
 |
WATCH
HERE THE PROJECT PROGRESS FOR
2010.
WATCH
HERE THE PROJECT PROGRESS FOR THE PERIOD OF
2007-2009.