December 2010 |
 | |
 |
The surrounding areas reinstatement works in all stations of the extension are in progress. |
 |
The works for the construction of the permanent lining at the natural lighting shaft of ALIMOS Station have been completed. |
|
|
 |
|
November 2010 |
| |
 |
The works concerning the installation of false ceilings at ELLINIKO and ARGYROUPOLI Stations are in progress. |
 |
The works for the construction of the metal sheds in all the station entrances of this extension are in progress. |
 |
The planting works at the main traffic island of Vouliagmenis Avenue at the point where it meets Ag. Vassiliou Shaft will soon be completed. |
|
|
 |
|
October 2010 |
 | |
 |
The installation of false ceilings commenced in ELLINIKO Station area. |
 |
The waterproofing works of the permanent lining for the construction of the natural lighting shaft in ALIMOS Station commenced. |
 |
Placement anew of the antiquities at the surface level of ALIMOS Station is in progress. |
 |
The installation of surveillance systems (cameras) in all stations of the extension is in progress. | |
|
 |
|
September 2010 |
 | |
 |
The temporary retaining works for the construction of the natural lighting shaft at the inclined underground passageway crossing Vouliagmenis Avenue have commenced at the concourse level of ALIMOS Station. |
 |
The installation of cabling for the systems of lighting, telecommunications and loudspeakers continues in all the stations of the extension. |
 |
The reinstatement of the surrounding area in ARGYROUPOLI and ELLINIKO Stations as well as in the Depot is in progress. | |
|
 |
|
August 2010 |
 | |
 |
The traffic reinstatement of Vouliagmenis Avenue at the intersection of Agiou Vassileiou Shaft is in progress. |
 |
The Civil Works at the tunnel connecting the Eastern Entrance with ALIMOS Station have been completed. |
|
|
 |
|
July 2010 |
|
| |
 |
The excavation works of the gallery connecting the Eastern entrance with ALIMOS Station have been completed. |
 |
The backfilling works, along with the works for the reinstatement of the surrounding area at the stations and the ventilation shafts of the extension, are in progress. |
 |
The works for the installation of metal structures and stainless steel finishes in stations’ areas are in progress. |
|
|
 |
|
June 2010 |
|

| |
 |
Phase A’ of the excavation works of the tunnel connecting the Eastern Entrance with ALIMOS Station has been completed. |
 |
The reinstatement of the surrounding areas of ELLINIKO and ARGYROPUPOLI Stations is in progress. |
 |
The installation of metal sheds at the stations’ entrances is in progress. |
|
|
 |
|
May 2010 |
|

| |
 |
The works for the construction of retaining walls and the reinstatement of the surrounding area in ARGYROUPOLI Station are in progress. |
 |
The works for connecting the extension of the project to the existing Lyssiou Shaft, have commenced in cooperation with AMEL. |
 |
A’ Phase excavation works relating to the tunnel connecting the Eastern Entrance with ALIMOS Station are in progress. |
|
|
 |
|
April 2010 |
|

| |
 |
The boring of the connecting tunnel at the eastern entrance with ALIMOS Station commenced. |
 |
Works related to floor and wall cladding with granite at ALIMOS Station are at a completion phase. |
 |
The installation of stainless steel linings and the installation of lighting systems in the areas of the four stations and the underground Depot are in progress. |
|
|
 |
|
Ìarch 2010 |
|

| |
 |
The construction of the metal shed at the main entrances of ELLINIKO and ARGYROUPOLI Stations is at an advanced stage. |
 |
Works related to the construction of the permanent lining of the eastern entrance at ALIMOS Station is in progress. |
 |
The re-development of the area above the underground Depot of the extension is still under way. |
|
|
 |
|
February 2010 |
|
| |
 |
Works related to the permanent lining of the Western Entrance at ILIOUPOLI Station were completed. |
 |
The re-development of the surrounding area at ARGYROUPOLI Station commenced. |
 |
Works related to the installation of electromechanical equipment and networks at all the stations are under way. |
|
|
 |
|
January 2010 |
|
| |
 |
Works related to the temporary retaining of the excavations at the Eastern Entrance of ALIMOS Station continue. |
 |
The installation of stainless steel linings and special structures in the interior of the stations. |
 |
The installation of metal sheds at the entrances of ARGYROUPOLI and HELLINIKO Stations commenced. |
|
|
 |