December 2010 |
| |
 |
The civil works at the car parking facility adjacent to the Station have been completed. This 4-storey car parking facility has a total capacity of 383 parking spaces. |
 |
The works for the installation of false ceilings at the concourse level are at an advanced stage. |
|
|
 |
|
November 2010 |
| |
 |
The works for the reinstatement of the northern entrance/exit of the Station are at an advanced stage. |
 |
The construction of the roof slab at the 2nd level of the car parking facility has been completed. |
|
|
 |
|
October 2010 |
| |
 |
The reinstatement works at the Northern entrance/exit of AGHIA MARINA (HAIDARI) Station are about to be completed. |
|
|
 |
|
September 2010 |
| |
 |
The construction of the ground floor slab at the Parking Facility has been completed. |
 |
The installation of granites at the station platform level has been completed, while the works for the reinstatement of the worksite area have commenced. |
|
|
 |
|
August 2010 |
| |
 |
The architectural works at the tunnel connecting the north access of the station with the concourse level are at a final stage. |
 |
The works for the construction of the foundation, the perimeter walls and the columns at the car parking facility are in progress. |
 |
The architectural works and the works for the installation of the electromechanical equipment at ELEONAS Station are in progress. |
|
|
 |
|
July 2010 |
| |
 |
The installation of waterproofing membranes in the Parking Facility of the Station is in progress. |
 |
The installation of false ceilings at the concourse level of AGHIA MARINA (HAIDARI) Station has commenced. |
 |
The works for the insulation of the roof of ELEONAS Depot auxiliary operations’ building are in progress. |
|
|
 |
|
June 2010 |
| |
 |
Covering works, as well as the installation of the electromechanical equipment at the DEPOT (running shed, washing plant) are at the final stage. The installation of the trackwork is about to be completed. |
 |
The installation of wall panels’ frame at AGHIA MARINA (HAIDARI) Station is in progress. |
|
|
 |
|
May 2010 |
| |
|
|
 |
|
Ápril 2010 |
| |
|
|
 |
|
Ìarch 2010 |
|

| |
|
|
 |
|
February 2010 |
|

| |
|
|
 |
|
January 2010 |
|

| |
 |
Architectural works at the platform level are in progress. |
 |
Architectural works at all the station levels are in progress (accesses etc). |
 |
The installation of rail tracks throughout the entire length of the extension is in progress. |
|
|
 |