December 2010 |
 | |
 |
By the end of 2010, the 2 TBMs had constructed a total of 7,628 meters of ready tunnel (single track). |
 |
The construction of the roof slab at the north part of FLEMING Station is completed. |
 |
The works for the temporary steel bridge at the south section of DEMOKRATIAS Station are in progress, while the archaeological survey is currently in progress. |
|
|
 |
|
November 2010 |
 | |
 |
The first TBM has constructed 3,826m. of complete tunnel and the second TBM 3,404m. |
 |
The excavation works at FLEMING & ANALIPSI Stations are in progress, while the PUO network diversion works have started at PATRIKIOU Station. |
|
|
 |
|
October 2010 |
 | |
 |
The construction of the diaphragm walls at 11 locations of the Project has been completed. |
 |
Until the present date, both TBMs have constructed 50% of the Metro tunnels. |
 |
The progress of the archaeological excavation works in the 5 central Stations has reached 40%. |
|
|
 |
|
September 2010 |
 | |
 |
The first Tunnel Boring Machine (TBM1) continues its drive having bored 3,496m of tunnel, while the second Tunnel Boring Machine (TBM2) has constructed 3,153m of the twin tunnel. |
 |
The works for the construction of the roof slab at EFKLIDIS Station are in progress. |
|
|
 |
|
August 2010 |
 | |
 |
The first Tunnel Boring Machine (TBM1), which has already bored 3,000m of tunnel, has been re-launched. The second Tunnel Boring Machine (TBM2) is anticipated to be re-launched soon (2,714m of tunnel). |
 |
The construction of the floor slab at the first underground level of EFKLIDIS Station is in progress. |
|
|
 |
|
July 2010 |
 | |
 |
The construction of the roof slab at FLEMING Station, PANEPISTIMIO Station and the NEW RAILWAY STATION is in progress. |
 |
The works for the PUO network diversions in ANALIPSI and PATRIKIOU Stations are in progress, while the works for the construction of the Diaphragm Walls at ANALIPSI Station have commenced. |
 |
The archaeological excavation works at the following positions of the Project, namely FLEMING Station, SINTRIVANI Station, AGHIA SOFIA Station, VENIZELOU Station, DIMOKRATIAS Station and NEW RAILWAY STATION, are in progress. | |
|
 |
|
June 2010 |
 | |
 |
The construction of diaphragm walls at PANEPISTIMIO and FLEMING Station is completed. |
|
|
 |
|
May 2010 |
 | |
|
|
 |
|
April 2010 |
 | |
 |
Works related to the construction of EFKLIDIS, PANEPISTIMIO and FLEMING Stations are in progress. |
 |
Works related to PUO network diversions at the eastern section of the project are in progress. |
|
|
 |
|
Ìarch 2010 |
 | |
|
|
 |
|
February 2010 |
 | |
|
|
 |
|
January 2010 |
 | |
 |
The second Tunnel Boring Machine (ÔÂÌ2) reached the worksite of the Station at PANEPISTIMIO, thus having constructed 2,720m of parallel tunnel. |
 |
The construction of diaphragm walls at EFKLIDIS Station was completed. |
|
|
 |