The most extensive front of Metro Projects ever performed in Greece is currently progressing at an intensive pace. All ATTIKO METRO employees make a co-ordinated effort on a daily basis to deliver the modern Metro Stations in several areas of Athens, in Aghia Marina, Ilioupoli, Alimos, Argyroupoli and Helliniko.

The Metro Line 3 extension, 4.3 km long, with 3 modern Stations extending from Monastiraki to Egaleo was commissioned in May 2007. The Metro network continues to be expanded with new Stations and the construction the 1.5 km-extension of Line 3 towards Aghia Marina, with one new Station and one depot in Eleonas area, was completed. The construction of this project has been completed. The installation of the signalling system by SIEMENS Company is at a completion phase. It is noted that this contracting work also had included the construction of a Parking Facility for Private vehicles, right next to the Station, with an overall capacity of 380 places.

Concurrently, one of the most extensive Municipalities in Greece, the Municipality of Peristeri, acquired two more new Metro Stations in April 2013, after the successful completion and operation of AGHIOS ANTONIOS Station in summer 2004. It is also pointed out that the relevant square of the Municipality that covers an area of 10,000 square meters in total has been configured and re-developed.

The project of the extension of Line 2 to Elliniko shall add to the Athens Metro network 5.5 klm of underground Line and 4 new Stations (ILIOUPOLI, ALIMOS, ARGYROUPOLI, ELLINIKO). The construction of the subject Project has been completed. The installation of the signalling system by SIEMENS Company is at a completion phase.

In December 2010, Line 3 northern end was fully developed with the commissioning of AGHIA PARASKEVI Station. HOLARGOS Station was commissioned earlier, July 2010 and NOMISMATOKOPIO Station in September 2009. In the framework of the same contracting work, a Bus Transfer Station is constructed in the area of NOMISMATOKOPIO station which is the first Metro Station on Messogion Avenue that can be used by commuters, residing in Aghia Paraskevi, Messogia region and the eastern suburbs of Attica region. An underground Parking Facility for private vehicles of a capacity of 630 places has also been delivered to public.

The Athens Metro, is now extending to Aghia Varvara, Korydallos, Nikea, Maniatika and Piraeus, with 6 new stations and 7.6 km. of underground line. More specifically, the Contract for the extension of line 3 to Piraeus with the constructing joint venture J&P AVAX, GHELLA SPA and ALSTOM TRANSPORT was signed in March 2013 and the construction of the project commenced. At present, the development of the worksite areas, the execution of archaeological works and the PUO relocations are in progress.

   
 
Print this page E-mail this page
    Last Updated: 10/6/2013
 
     