Homepage > Construction of the Athens Metro > Project Progress > Construction   Operation
Piraeus

On November 21st 2008 ATTIKO METRO S.A. proceeded to the re-procurement of the project related to Line 3 Metro extension to the Western Suburbs, terminating in the area of Piraeus (underground tunnel, 7.6 km long, with 6 modern stations: Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus, Dimotiko Theatro).

On February 13th 2009, 6 technical consortia/joint ventures expressed their interest in the construction of the project. On October 5th 2011, ATTIKO METRO S.A. proceeded to the unsealing of the Financial Offers for the Project concerning the extension of Metro Line 3 to Piraeus.

The classification order of the three bidding joint ventures, based on their Financial Offer, is as follows:

JOINT VENTURE

FINANCIAL OFFER

1. J&P – VX – GHELLA SPA – ALSTOM TRANSPORT SA

343.96 million €

2. AKTOR – R

349.00 million €

3. FCC CONSTRUCCION S.A. – ALPINE BAU GMBH

349.75 million €

Based on the aforementioned Tender results, J&P – VX – GHELLA SPA – ALSTOM TRANSPORT SA is the lowest-bidder of the Tender.

On March 1st 2012, the relevant contract was signed with the contracting joint venture J&P - AVAX S.A., GHELLA SPA, ALSTROM TRANSPORT S.A for the construction of Line 3 extension from Aghia Marina to Piraeus, 7.6 km long in total, with 6 modern Metro Stations. Attiko Metro S.A. was represented by Mr. Christos Tsitouras, Chairman of the BoD and Managing Director, while the Construction Joint Venture J&P VAX SA was represented by Mr. Konstantinos Mitzalis, Managing Director.

This Project constitutes a 660,000,000 EURO investment in areas of Piraeus Municipalities and other Municipalities in the wider area (Nikea, Korydallos, Aghia Varvara), which are currently faced with acute traffic problems and sub-standard services, in terms of Public Transport Modes.

The Metro Extension to Piraeus will serve approximately 132,000 passengers on a daily basis, while the distance between the Port and the International Airport will be covered by the Metro in just 45 minutes. Additionally, once the Metro becomes operational, the number of vehicles will be reduced by approximately 23,000 on a daily basis, leading to a respective daily reduction in CO2 by 119 tn.

Especially as regards Piraeus Station, a major Transportation Junction will emerge, connecting the two Metro Lines (Line 1 and Line 3), the Port, the Suburban Railway and the Tramway, which is also foreseen to pass through the same area, providing, thus, inter-modal transfers.

The Metro tunnel will be constructed using a Tunnel Boring Machine (TBM) in order to minimize the inevitable disturbance to the functions of the Municipalities; during the construction period (2012-2017) 2,000 persons in total are foreseen to be employed in this Project.

The extension of the Tramway from Neo Faliro to Piraeus centre recently commenced, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway network. More specifically, in January 2013 the contract was signed between ATTIKO METRO S.A. and the Company THEMELI S.A.

Apart from the Line 3 Extension to Piraeus, ATTIKO METRO S.A will shortly be engaged in the following projects as well, namely:

1.

Extension of the Tramway network from Neo Faliro to Piraeus centre, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway. The construction of this specific project commenced in September 2013 by ATTIKO METRO.

2.

Conversion of Line 1 (ISAP) section form N.Faliro to Piraeus into an underground structure, with the addition of one new station in the area of Keranis Factory, unifying, in terms of functions and town planning the areas of Piraeus currently served by the surface ISAP Line 1. The designs pertaining to this Project are about to be completed enabling, thus, ATTIKO METRO S.A. to put it to Tender.

3.

Extension to the Tramway Network to Keratsini - Perama, following an underground alignment at a large part of Keratsini Municipality, running along the alignment of the old Perama tramway. The Advanced Concept Designs regarding this Project are underway.



LINE 3 EXTENSION TO PIRAEUS


Location of the Stations

Aghia Varvara   Eleftheriou Venizelou Av. (Ag. Eleoussa)
Korydallos Eleftherias Square
Nikaia El.Venizelou Square
Maniatika Etolikou & Mavromihali Str.
Piraeus Port (close to ISAP station)
Dimotiko Theatro Iroon Polytechniou & Vassileos Georgiou






Tunnel
6,5km of the tunnel of the extension will be constructed using the Tunnel Boring Machine, while the remaining parts at the beginning and at the end of the project will be constructed via the underground excavation method.

Shafts
8 ventilation shafts in total shall be constructed along the new Line and two shafts for the TBM’s entering/exiting.


PROGRESS OF WORKS

August 2014
































NIKEA Station: The works for the construction of a foundation earthing system, soil improvement works and works for the acceptance of the main Station foundation invert have been completed. Excavation works and works for the removal of the muck (removal of the excavated material from the Station NATM tunnel access), as well as works for the waterproofing of the foundation slab and perimeter walls, the construction of the main Station permanent lining (concreting of the foundation slab from axes 8-12) and the excavation and retaining of Station NATM tunnel (phase A) are in progress;

MANIATIKA Station: Excavation works up to level 9, shotcrete application up to level 8, the construction of pre-stressed anchors up to level 8 of the Station main building and the construction of fully embedded rock bolts are in progress;

PIRAEUS Station: The works concerning EPA, water-supply, OTE networks and other providers’ networks within the OLP area, as well as the connections of the natural gas pipe transverse to Akti Kallimasioti have been completed. In the framework of the traffic arrangements, the removal of stop sheds and ticket issuing offices, as well as the works for the relocation of the kiosk located at the west sidewalk at the south end of the diversion has been completed. Moreover, the construction of water-supply networks, slabs for storm-water duct protection and the construction of manholes for the water-supply network and OLP valves have been completed. The works for the extension of the worksite occupation surface/ fencing, the construction of road-paving layers (base, sub-base), the construction of a temporary wall for OLP’s fencing, the construction of OLP balustrades and the relevant protection for OTE and PPC networks are in progress;

DIMOTIKO THEATRO Station: The works for the excavation and installation of a temporary retaining system (shotcrete – pre-stressed anchors)/ 1st excavation bottom (+10.00) have been completed, while the archaeological investigations for ancient wells and tanks, the preservation of the Project’s archaeological finds, and the excavation and installation of a temporary retaining system (shotcrete – pre-stressed anchors) for the 2nd excavation level in Aghiou Konstantinou Square are in progress. The works -in the framework of the archaeological excavations- for the removal of earth from the trench at the Ventilation Shaft are in progress;

The works for the detachment of archaeological finds (pebbled floor) for preservation purposes have been completed, while the works for the construction of temporary retaining piles in Deligianni Shaft are in progress;

Tunnel excavation works have been completed by 17%.

July 2014















AGHIA VARVARA Station: The works for the construction of the platform columns and floor slab are currently in progress;

KOLYDALLOS Station: Completion of the works related to the drilling, embedding and tensioning of the pres-stressed anchors, as well as of the Station’s raft concreting works;

NIKEA Station: In progress are the works for the construction of the Foundation Earthing, as well as for the temporary drainage of the floor of the final excavation level of the main Station’s C/C part (axes 8-15);

MANIATIKA Station: Completion of the pile cap beam construction works - In progress are the works for the excavation of the 7th and 8th levels, the application of the shotecrete and the construction of the pre-stressed anchors at level 7 of Station’s main structure;

PIRAEUS Station: Completion of the drilling operations for the construction of a water-jet drilling, the installation of piezometers and trial pumping at access 3, as well as the works for the demolition of three small buildings. The works for dismantling gates E5 and E6 are also completed. Still in progress are the works for the construction of the natural gas pipe networks at the location where PUO diversion works are executed. Moreover, in the framework of the traffic arrangement, completion of the construction of the industrial floor and the water supply manholes in view of changing the ships mooring location, the arrangement of EYDAP’s pumping station corridor and the configuration of the surrounding area, the construction of new walkways in the area of Gate E7 and the relocation of OLP’s lighting pole; at the same time, in progress are the works for the construction of the stormwater drainage network, the construction of traffic lights network, the construction of ILPAP network and the construction of the street lights;

DIMOTIKO THEATRO Station: Completion of the works for the construction of piles and pile cap beams at Aghiou Konstantinou square, as well as of the works for the construction of the temporary retaining piles at Korai Square;

Completion of EYDAP network diversion works at Deligianni Shaft; completion of dismantling/removal works in the section located inside the yard area of the University at Panepistimio Shaft; archaeological excavations in this area are in progress;

Commencement of the tunnel boring operations for the 2nd interstation; 12% completed so far.

June 2014



 

 

 

 












 


NIKEA Station: The excavation and muck disposal, as well as the construction of the temporary retaining (shotcrete, prestressed anchors, metal struts) at levels 5 and 6 of the main Station were completed. The excavation and disposal of excavation spoils of the main Station (levels 7, 8 and final excavation level), the construction of prestressed anchors of levels 7 and 8 of the main Station, the laying of shotcrete at levels 7, 8 and at the final excavation level of the main Station, the improvement and acceptance of the final excavation floor of the main Station’s C/C and the construction of NATM tunnel (Phase A’) of the Station are in progress;

MANIATIKA Station: The excavation, the laying of shotcrete and the construction of prestressed anchors at level 6 of the Station’s main building are in progress;

PIRAEUS Station: The worksite occupation / fencing of a part of access 2 and the diversion of fiber optics C4i, fiber optics of OLP/PPC/water supply and natural gas in OLP area were completed. Moreover, the construction of a temporary bridge at the NW edge of the pier, the installation of new passenger waiting areas, new WCs at new locations and the reduction of the sidewalk width at Kononos street, as well as the construction of new curbs were completed;

DIMOTIKO THEATRO Station: The construction of the building crane and the archaeological excavation at Aghiou Konstantinou square were completed, while the works for the reinstatement of the Archaeological Service building to be utilized for the storage, conservation and transfer of archaeological finds of the Project are in progress. The works for the construction of temporary retaining piles (33/51 piles) in Korai square are in progress;

The archaeological excavation at Deligianni Shaft was completed. The Central Archaeological Council (CAC) gave its expert opinion on the preservation of the pebble floor and the non-preservation of the remaining archaeological finds. The preparation of the design concerning the detachment of archaeological finds listed for preservation (pebble floor) was completed, while the works for the detachment of the subject finds are in progress;

The TBM maintenance works is completed prior to the commencement of the excavation works at the 2nd interstation.

May 2014



















KORYDALLOS Station: The works for the general excavation of the Station and the works for the improvement of the foundation invert – placement of a drainage layer have been completed. Waterproofing works, the works for the placement of reinforcement and foundation slab concreting works are in progress.

NIKEA Station: Excavation works and the works for the removal of the excavation spoils from the 1st up to the 4th level of the station have been completed. Excavation works, the works for the removal of the excavation spoils, concreting works at the 4th up to the 8th level and at the final excavation level are in progress. The works for the permanent lining of the main Station are also in progress.

MANIATIKA Station: The works for the diversion of PUO networks (sewage, water-supply, telephony, power supply), excavation works at the 4th and the 5th level of the main building of the station, shotcreting works and works for the construction of prestressed anchors at the 3rd, 4th and 5th level have been completed.

PIRAEUS Station: The investigation trench drilled to locate the foundations of ISAP building has been completed, as well as the archaeological investigation trenches in a section of access 2 and the works for the dismantling of the sheds in access 2. The works for the dismantling of existing structures, as well as works for the excavation of archaeological investigation trenches in access 3 have also been completed.

DIMOTIKO THEATRO Station: The archaeological works and works for the construction piles for temporary retaining are in progress. The archeological investigation and the excavation works at the perimeter of the excavation in Korai Square have been completed. The archaeological works in Bakogianni Square are in progress.

Tunnel boring works have been completed by 7%.

April 2014


 



 

 

 




 


The works for the construction of cap beam, excavation and temporary retaining, temporary drainage of the raft and the construction of the foundation slab are completed, while waterproofing works and works for the construction of walls are in progress at AGHIA VARVARA Station;

The worksite fencing, as well as the archaeological investigation trenches at Taxiarchon Shaft of AGHIA VARVARA Station, were completed;

The works for the construction of piles and the cap beam at KORYDALLOS Station were completed, while the general excavation at the final level is at the final level (level 7);

The works for the construction of piles and the cap beam, as well as the temporary retaining of NIKEA Station, were completed, while waterproofing works of the foundation slab and the construction of prestressed anchors are in progress (levels 4 to 8);

The works for the construction of piles and the archaeological excavation were completed, while the excavation at levels 2 and 3 are in progress at the main building of MANIATIKA Station;

The worksite occupation for the PUO diversions, as well as the diversion of the gas pipe in OLP area at PIRAEUS Station are completed. Moreover, the investigation archaeological trenches for the identification of ISAP building sewage pipe were completed;

The relocation of PUO networks, as well as the installation of a building crane were completed, while the works for the construction of temporary retaining piles at Aghiou Konstantinou square, at DIMOTIKO THEATRO Station, are in progress;

The tunnel excavation has been completed to 5%.

March 2014





The works for the construction of the temporary retaining piles at AGHIA VARVARA Station are completed, while the works for the temporary discharge of the invert and the waterproofing works are in progress;

The installation of the drainage layer on the invert of KORYDALLOS Station is in progress;

The drainage of the final floor of NIKEA main station C/C excavation is in progress;

The works related to the excavation of the 1st and 2nd levels of MANIATIKA Station main building, as well as the construction of prestressed anchors, are in progress.

February 2014








The archaeological investigation trenches in Komninou Shaft were completed;

The works for the construction of the foundation slab in AGHIA VARVARA Station are in progress;

The general excavation works at the final level of KORYDALLOS Station are at an advanced stage;

Shotcrete works up to the 8th level of NIKEA Station are at an advanced stage;

The works for the diversion of the sewage water network, PPC, EPA, water supply, OTE optic fibres and supplies in Piraeus Port Authority S.A. (OLP) area in PIRAEUS Station are in progress;

The works for the transfer of the archaeological finds in a storage and conservation room, as well as the installation of a building crane at Aghiou Konstantinou square, at DIMOTIKO THEATRO Station, are in progress.

January 2014



The general excavation (6th level) along with the temporary retaining structures in the area of KORYDALLOS Station are at a completion percentage of 89%;

The worksite fencing in TAXIARCHON Shaft in AGHIA VARVARA Station is in progress;

The main excavation works in the area of NIKEA Station (C/C) is at percentage of 66%, while the construction of pre-stressed anchors is at percentage of 72%;

The construction of piles in the area of MANIATIKA Station is in progress.

December 2013









The works for the diversion of sewage and water supply networks at Komninou Shaft have been completed;

The works for the construction of cap beam at AGHIA VARVARA Station are in advanced stage;

The drilling, embedment and tensioning works of the prestressed anchors at KORYDALLOS Station are in progress;

The excavation and shotcrete related works at NIKEA Station (5th level) are at an advanced stage;

The worksite occupation and fencing at MANIATIKA Station are in progress;

The archaeological investigation trenches in Piraeus Port Authority S.A. (OLP) area at PIRAEUS Station are completed;

The archaeological excavation at the NE part of Korai Square is in progress, while this excavation has been completed at Deligianni Shaft.

November 2013


The first 44 out of the overall 6,346 meters of the Project’s tunnel have already been bored and 43 out of the 4,243 rings have already been installed;

The general excavation of KORYDALLOS Station is at an advanced stage, since the subject Station is at the 4th excavation level;

The works for the construction of pre-stressed anchors, as well as the shotcreting works in all levels (1st, 2nd, 3rd and 4th) of excavation in the main NIKEA Station are in progress;

The construction of the diversion, which is necessary for the construction of piles in DIMOTIKO THEATRO Station, was completed;

The works for the networks’ diversion in MANIATIKA Station were completed.

October 2013


The works for the construction of the foundation slab at the TBM start-up shaft have been completed;

The works for the construction of the pile cap beam of AGHIA VARVARA Station are in progress;

The works for the excavation and the temporary retaining of KORYDALLOS Station are in progress;

The works for the construction of piles and the pile cap beam of NIKEA main Station have been completed, while the works for the construction of the entrances’ piles are in progress;

The Archaeological investigation in the section under occupation has been completed, while the investigation of the archaeological wells/reservoirs in P. Bakoyianni Square in the area of DIMOTIKO THEATRO is in progress;

The traffic arrangement for the construction of MANIATIKA Station is in progress;

The worksite occupation (Phase A’) is at the completion stage, while the configuration of the occupation boundaries to the southern side of Odyssou Square in the area of PIRAEUS Station is in progress.

September 2013


The excavation and retaining works of the NATM tunnel towards Piraeus at the TBM Access Shaft, as well as the drainage and waterproofing of the shaft's bottom have been completed;

The excavation works in AGHIA VARVARA Station are in progress, while the construction works for temporary retaining piles have been completed;

The Piles and the Pile cap beam of the main Station, as well as the configuration of the new roadwork ar the perimeter of Eleftherias Square in KORYDALLOS Station have been completed;

The worksite occupation and the fencing, as well as the archaeological excavation in the open cut area on Petr. Mavromichali Street in MANIATIKA Station are in progress.

August 2013



The assembly of the Tunnel Boring Machine (TBM) in the Access Shaft is at the completion stage;

The works for the construction of piles and the pile cap beam in KORYDALLOS Station are in progress;

The dismantling works at the surface level and the works for the PUO networks diversion in the area of NIKEA Station are in progress;

The construction of the passageways was completed, while the networks diversion works onthe sidewalks in DIMOTIKO THEATRO Station are in progress.

July 2013

The worksite installation works, as well as the assembly of the Tunnel Boring Machine (TBM) at the TBM access shaft are in full swing.

The 3rd phase of the traffic arrangement in the area of KORYDALLOS Station is in full operation.




June 2013









The works for the construction of the foundation slab (reinforcement and concreting) and the drilling of the forepoles towards Piraeus at the TBM access shaft were completed, while the excavation works for the retaining of the NATM tunnel to AGHIA MARINA Station in the Municipality of Aghia Varvara are in progress;

The archaeological works and the investigation trenches, at the western sidewalk of El. Venizelou Street in the area of AG. VARVARA station, were completed;

Phase 1 of the traffic arrangement at the perimeter of KORYDALLOS Station and the construction of the sidewalks to the shops’ side has been completed and is fully operating;

The archaeological trenches, the diversion of OTE network on Dimitrakopoulou Street, as well as the demolitions of expropriated buildings in the area of MANIATIKA Station are in progress;

The archaeological excavations in the occupied section of Ag. Konstantinou Square at DIMOTIKO THEATRO Station were completed.

May 2013


The works for the PUO network diversions were completed in AGHIA VARVARA Station, while the worksite installations and the pile construction works for the temporary retaining of the Station are in progress;

The investigation trenches for the identification of the foundations of the Piraeus Port Authority S.A. (OLP) pedestrian bridge in PIRAEUS Station were completed;

The worksite occupation/fencing in Ag. Konstantinou Square at DIMOTIKO THEATRO Station is about to be completed soon along with the relocation of the last kiosks. In addition, the archaeological excavation works are in progress.

April 2013



The works for the drilling of forepoles towards Piraeus at TBM start-up Shaft are in progress;

The archaeological excavation works at the south and north-eastern section of the main station, as well as the traffic regulations for the diversion of OTE network at Grevenon Street in NIKEA Station have been completed;

The diversion of the sewage network at P. Mavromichali Street in MANIATIKA Station has been completed;

The works for the diversion of the stormwater network in AGHIA VARVARA Station are in progress.

March 2013


The works for the construction of temporary retaining piles and the pile cap beam at the TBM start-up shaft have been completed;

The works for the dismantling of shop sheds, as well as for the construction of new sidewalks at the eastern and southern part of Eleftherias square at KORYDALLOS Station, have been completed;

The works for the diversion of PPC and OTE networks, as well as the traffic arrangements at El. Venizelou street at AGHIA VARVARA Station, have been completed.

February 2013


The first phase of the traffic arrangement has been completed and is in full swing, while the works for the construction of new sidewalks at the perimeter of Eleftherias Square in KORYDALLOS Station area, as well as the diversions of the PUO networks are in progress;

The relocation of kiosks in Odyssou Square along with the archaeological investigation works are in progress;

The investigation works for the sewage and storm water networks’ routing in Odyssou Square in PIRAEUS Station area are in progress;

The archaeological works in KORYDALLOS Station have been completed; no significant archaeological finds have been revealed, while the supplementary archaeological trenches are to commence soon;

The PUO network diversions in NIKEA Station area, as well as the traffic arrangement at the southern section of the station along Efessou Street are in progress.


January 2013

Phase A’ of the traffic diversion at KORYDALLOS Station has been completed;

Archaeological excavations at the Tunnel Boring Machine (TBM) Startup Shaft have been completed;

PUO network relocations at AGHIA VARVARA Station are at a completion phase.



December 2012

Excavation works in the Tunnel Boring Machine (TBM) startup shaft have commenced.

Signaling works for the implementation of traffic arrangements at KORYDALLOS Station are in progress.




November 2012

The construction of retaining piles in the TBM startup shaft has been completed and excavation works are in progress.

All works related to the dismantling of various items, relocations of kiosks and transplantations have been completed in the six (6) stations of the Project and the archaeological survey, as well as the PUO network diversions, are in progress.


October 2012


The pile driving works at the TBM Start-up Shaft have been completed;

The relocation of the Public Utility Organizations networks is in progress at AGHIA VARVARA Station;

The archaeological survey is in progress at AGHIA VARVARA, NIKEA, KORYDALLOS and DIMOTIKO THEATRO Stations;

The worksite occupation related works are in progress at Odyssos Square (PIRAEUS Station) and Korai Square (DIMOTIKO THEATRO Station).

September 2012


The works for the construction of temporary retaining piles in the TBM access shaft are in progress;

The archaeological survey in KORYDALLOS Station area is at an advanced stage;

The worksite installation of the Contractor in MANIATIKA Station area has been completed;

The works for the relocation of the kiosks located within the construction boundaries of DIMOTIKO THEATRO Station will commence soon.

August 2012


The archaeological excavation in the TBM start up shaft in the area of Aghia Varvara is completed;

The dismantling and transplantation works, as well as the execution of investigation trenches for PUO networks in AGHIA VARVARA, NIKEA and KORYDALLOS Stations are at an advanced stage;

The work site occupation of the Contractor in DIMOTIKO THEATRO is in progress.

July 2012



The archaeological investigation at the Start-up Shaft of the Tunnel Boring Machine (TBM) in the area of Aghia Varvara is in progress.

The worksite occupation in KORYDALLOS and NIKEA Stations is in progress.

The Supplementary Boreholes Plan along the Metro Extension to Piraeus has been completed.



June 2012

The worksite occupation in the area of Aghia Varvara has commenced from where the Tunnel Boring Machine will start its journey with direction to Piraeus.

The boreholes' program along the extension to Piraeus is at a completion stage.




May 2012

The complementary boreholes campaign along the Metro Extension to Piraeus is in progress.






April 2012

ATTIKO METRO S.A. in cooperation with the Joint Venture J&P S.A. -- Ghella SpA -- Alstom Tranport S.A. is performing all necessary survey works for the construction of the Metro Extension to Piraeus.






   
 