Piraeus

On November 21st 2008 ATTIKO METRO S.A. proceeded to the re-procurement of the project related to Line 3 Metro extension to the Western Suburbs, terminating in the area of Piraeus (underground tunnel, 7.6 km long, with 6 modern stations: Aghia Varvara, Korydallos, Nikaia, Maniatika, Piraeus, Dimotiko Theatro).

On February 13th 2009, 6 technical consortia/joint ventures expressed their interest in the construction of the project. On October 5th 2011, ATTIKO METRO S.A. proceeded to the unsealing of the Financial Offers for the Project concerning the extension of Metro Line 3 to Piraeus.

The classification order of the three bidding joint ventures, based on their Financial Offer, is as follows:

JOINT VENTURE

FINANCIAL OFFER

1. J&P – VX – GHELLA SPA – ALSTOM TRANSPORT SA

343.96 million €

2. AKTOR – R

349.00 million €

3. FCC CONSTRUCCION S.A. – ALPINE BAU GMBH

349.75 million €

Based on the aforementioned Tender results, J&P – VX S.A. – GHELLA SPA – ALSTOM TRANSPORT SA is the lowest-bidder of the Tender.

On March 1st 2012, the relevant contract was signed with the contracting joint venture J&P - AVAX S.A., GHELLA SPA, ALSTROM TRANSPORT S.A for the construction of Line 3 extension from Aghia Marina to Piraeus, 7.6 km long in total, with 6 modern Metro Stations. Attiko Metro S.A. was represented by Mr. Christos Tsitouras, Chairman of the BoD and Managing Director, while the Construction Joint Venture J&P VAX SA was represented by Mr. Konstantinos Mitzalis, Managing Director.

This Project constitutes a 730,000,000 EURO investment in areas of Piraeus Municipalities and other Municipalities in the wider area (Nikea, Korydallos, Aghia Varvara), which are currently faced with acute traffic problems and sub-standard services, in terms of Public Transport Modes.

The Metro Extension to Piraeus will serve approximately 132,000 passengers on a daily basis, while the distance between the Port and the International Airport will be covered by the Metro in just 45 minutes. Additionally, once the Metro becomes operational, the number of vehicles will be reduced by approximately 23,000 on a daily basis, leading to a respective daily reduction in CO2 by 120 tn.

Especially as regards Piraeus Station, a major Transportation Junction will emerge, connecting the two Metro Lines (Line 1 and Line 3), the Port, the Suburban Railway and the Tramway, which is also foreseen to pass through the same area, providing, thus, inter-modal transfers.

The Metro tunnel will be constructed using a Tunnel Boring Machine (TBM) in order to minimize the inevitable disturbance to the functions of the Municipalities; during the construction period (2012-2017) 2,000 persons in total are foreseen to be employed in this Project.

The extension of the Tramway from Neo Faliro to Piraeus centre recently commenced, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway network. More specifically, in January 2013 the contract was signed between ATTIKO METRO S.A. and the Company THEMELI S.A.

Apart from the Line 3 Extension to Piraeus, ATTIKO METRO S.A will shortly be engaged in the following projects as well, namely:

1.

Extension of the Tramway network from Neo Faliro to Piraeus centre, completing, thus, the direct connection of the coastal axis with Piraeus through the Tramway. The construction of this specific project commenced in September 2013 by ATTIKO METRO.

2.

Conversion of Line 1 (ISAP) section form N.Faliro to Piraeus into an underground structure, with the addition of one new station in the area of Keranis Factory, unifying, in terms of functions and town planning the areas of Piraeus currently served by the surface ISAP Line 1. The designs pertaining to this Project are about to be completed enabling, thus, ATTIKO METRO S.A. to put it to Tender.

3.

Extension to the Tramway Network to Keratsini - Perama, following an underground alignment at a large part of Keratsini Municipality, running along the alignment of the old Perama tramway. The Advanced Concept Designs regarding this Project are underway.



LINE 3 EXTENSION TO PIRAEUS


Location of the Stations

Aghia Varvara   Eleftheriou Venizelou Av. (Ag. Eleoussa)
Korydallos Eleftherias Square
Nikaia El.Venizelou Square
Maniatika Etolikou & Mavromihali Str.
Piraeus Port (close to ISAP station)
Dimotiko Theatro Iroon Polytechniou & Vassileos Georgiou






Tunnel
6,5km of the tunnel of the extension will be constructed using the Tunnel Boring Machine, while the remaining parts at the beginning and at the end of the project will be constructed via the underground excavation method.

Shafts
8 ventilation shafts in total shall be constructed along the new Line and two shafts for the TBM’s entering/exiting.


PROGRESS OF WORKS

July 2015


AGHIA VARVARA Station: The works for the construction of the roof slab are in progress;

NIKEA Station: The TBM maintenance works and those for the construction of a portion of the main station’s roof slab are in progress;

MANIATIKA Station: In progress are the works for the construction of the pre-stressed anchors and rock anchors of the Station main building;

PIRAEUS Station: In progress are the bentonite production and curing works for the construction of DWs. Also in progress are the works for the construction of part of the rain water network. The works for the diversion of PUO networks were completed. At Roloi shaft, in progress is the archaeological excavation;

DIMOTIKO THEATRO Station: In progress are the works pertaining to the conservation of the archaeological finds and to the preparation of the exhibition area for the revealing and promotion of these finds in the building located at Pylon street, property of the Department of Antiquities;
Dimotiko Theatro ventilation shaft: the archaeological excavation is at the completion stage;
Panepistimio shaft: The archaeological investigation in the areas where PUO networks are to be diverted is in progress;

Tunnel boring works have been completed by 50%.

June 2015








AGHIA VARVARA Station: The works for the construction of columns down to the concourse level have been completed, while the works for the construction of access 3 are in progress;

KORYDALLOS Station: The removal of the launch cradle and the TBM false tunnel precast segments has been completed. The undisturbed cutting of the precast segments for TBM drive are in progress;

NIKEA Station: The works for the concreting of fixed staircases and escalators nos. 1, 2, 3, 4, 8, 9 from the platform level to the mechanical floor slab level have been completed. Completed are also the works for the concreting of staircase no. 5 (level +7.00 down to +13.12), no. 6 (level +6.90 down to +24.17) and no. 7 (level +6.90 down to +24.26). The works for the construction of mezzanine floor at the concourse level (level +16.22). TBM maintenance works are in progress;

MANIATIKA Station: In progress are works for the 12th level of the Station’s main building and for the application of shotcrete at the 11th level in the c/c area at Mavromichali street. The works for the conversion of the PPC network into an underground network and for reinstating part of the paving at the north sidewalk at Gythiou street have been completed;

PIRAEUS Station: Completed are the works related to the dismantling of old networks, while in progress are the works for the construction of part of the stormwater network;

DIMOTIKO THEATRO Station: The works related to the waterproofing and the concreting of the foundation slab and the perimeter walls down to the platform level of the main Station are in progress. At the entrance on Korai square in progress is the installation of a temporary retaining system (shotcrete – prestressed anchors – struts), the works for the excavation of the 3rd bottom (+1.00). Moreover, completed is the construction of temporary retaining piles at the Station entrance (31/33) on P. Bakogianni square. Phases A’ and B’ of the excavation works (progress of excavation works 18m/140m) were completed at the triple track NATM tunnel towards the University of Piraeus; phase A of the excavation works (progress of excavation works 18m/140m) is in progress (progress rate: 27/63m) towards Dimotiko Theatro (Municipal Theatre);

Tunnel excavation works have been completed by 50%.

May 2015




























AGHIA VARVARA Station: The roof slab construction works are in progress;

KORYDALLOS Station: Works for the construction of Station access piles have been completed, while the partial relocation of the TBM worksite installations is in progress;

NIKEA Station: The works for the concreting of columns up to the mechanical floor slab and the construction of interior walls and a part of the mezzanine slab (level +16.07) were completed. In progress are the works for the construction of exterior perimeter walls and columns from the E/M slab level up to the roof level, the construction of a part of the roof slab, as well as the construction of fixed staircases No. 8 and 9 from the concourse level up to the E/M slab level in the main Station. The geological investigation in Vlahakou shaft is in progress;

MANIATIKA Station: Completed are the works for the diversion of PUO networks (sewage, water supply, OTE, PPC), the demolition of expropriated buildings, the archaeological excavation and the construction of a cap beam and piles of the Station’s main building in the C/C area at Petr. Mavromichali street. In progress are works for the excavation of the 10th and 11th levels of the Station’s main building, the application of shotcrete at the 9th and 10th levels, the construction of pre-stressed anchors at the 8th level of the Station main building, and the construction of rock anchors (4th and 5th rows) in the same area. In progress is also the excavation and backfilling of trenches in view of the conversion of the PPC network into an underground network at the emergency exit, at Gythiou street;

PIRAEUS Station: In progress are the works related to the worksite installation and the construction of a washing plant, southern of axis 16. Completed are the works related to the dismantling of the existing structures (phase A’), the investigation of archaeological trenches, the diversion of PUO networks and the traffic arrangement;

DIMOTIKO THEATRO Station: The works related to the excavation and installation of a temporary retaining system were completed. In progress are the works related to the foundation earthing and drainage at the final excavation level, as well as to the waterproofing of the foundation slab and perimeter walls at the remaining section (46m) of the main Station. At the underground section of the Station, the construction of the 1st row of forepoles was completed, while at the entrance of Korai square in progress is the installation of a temporary retaining system (shotcrete – prestressed anchors – struts), 3rd excavation bottom (+4). In progress is also the construction of temporary retaining piles at the Station entrance (31/33) at P. Bakogianni square;

The TBM maintenance and the partial relocation of the TBM worksite related works at the double track tunnel are in progress. Phases A’ and B’ of the excavation works (progress of excavation works 8.6m/140m) were completed at the triple track NATM tunnel towards the University of Piraeus; phases A’ and B’ of the excavation works (2nd row of forepoles) were also completed, while the rate of progress of excavation works is 18/63m at the triple track NATM tunnel towards Dimotiko Theatro (Municipal Theatre).

April 2015





AGHIA VARVARA Station: The works for the construction of columns up to the ceiling level were completed, while the woks for the construction of perimeter walls up to the ceiling level and the roof slab construction works are in progress;

KORYDALLOS Station: Works for the construction of Station access piles are in progress;

NIKEA Station: The works for the waterproofing and concreting of the main station NATM tunnel have been completed. TBM sliding works, as well as works for the erection of scaffoldings and the construction of the formwork for the concreting of staircases No. 5, 6 and 7, in the framework of the construction of the Station’s permanent lining, are in progress;

MANIATIKA Station: The works for the excavation of the 6th, 7th, 8th, 9th and 10th level of the station main building are in progress. In progress are also the works for the application of shotcrete at the 6th, 7th, 8th and 9th level, the construction of pre-stressed anchors at the 6th and 7th level of the station main building, and the works for the construction of rock anchors (2nd, 3rd and 4th row) in the C/C area at P. Mavromichali Street;

PIRAEUS Station: Completed are the works related to the DW equipment assembly and the execution of a drilling and the installation of a piezometer. In progress are the works for the construction of Station guide walls, as well as the bentonite production and curing for the construction of DWs. In the framework of PUO network diversions, in progress are the diversions – EPA/PPC/water supply/sewage/OTE and suppliers/ILP fibre optics and C4i networks - within OLP area, as well as the diversion of the following networks: EPA, PPC MV and LV, OTE, ON, CYTA, FORTHNET, HOLL, water supply;

DIMOTIKO THEATRO Station: The waterproofing and concreting works of the foundation slab and the perimeter walls up to the platform level in the 1st section (30m long) at Aghios Konstantinos Square were completed. In progress are the preparatory works for the construction of piles at P. Bakogianni square, as well as construction works for the diversion of a sewage network and of OTE network diversion overpasses at Panepistimio shaft;

Phases A’ and B’ excavation works (1st row of spiles) were completed (excavation progress 3m/140m at the single track tunnel to the University of Piraeus), while phase A’ excavation works (left half-section) (2nd row of spiles) (progress of phase A’ excavation 4.5m/140m) are in progress. Phase A’ and B’ excavation works (1st series of forepoles) (progress of excavation works 9/63) for the triple track NATM tunnel towards Dimotiko Theatro (Municipal Theatre) - were completed, while works for the construction of the 2nd row of forepoles are in progress;

Tunnel boring works have been completed by 50%.

March 2015








AGHIA VARVARA Station: Excavation works and works for the construction and tensioning of pre-stressed anchors in Taxiarchon Shaft are in progress;

KORYDALLOS Station: Waterproofing, permanent lining reinforcement and concreting works are in progress;

NIKEA Station: The works for the waterproofing for the main station foundation slab, the concreting of the columns up to the concourse level slab, the concreting of the staircases and escalators nos. 1, 3 and 4 up to the concourse level slab, the concreting of staircases nos. 6 and 7 up to the E/M slab, waterproofing of the main station NATM tunnel, the concreting of the vault and the concreting of TBM bed inside the station NATM tunnel have been completed. The works related to the construction of the TBM bed are in progress, while the works for the installation of steel reinforcement for proceeding with the concreting of part of the roof slab and the works for the installation of steel reinforcement at the interior walls supporting the slab of the mezzanine floor at the concourse level are also in progress;

MANIATIKA Station: The works for the excavation of the 5th, 6th level (access ramp area) and the 8th, 9th and 11th level of the station main building are in progress. In progress are also the works for the application of shotcrete and the construction of pre-stressed anchors at the 5th level of the station main building (access ramp area) in the open trench area of P. Mavromichali Street. Works for the excavation and phase A2 temporary retaining (south face – western gallery) of the station’s main tunnel are also in progress;

PIRAEUS Station: Completed are the works related to a) the excavation of two diaphragm walls (DW) testing panels, b) the execution of three drillings and the installation of magnetic extensometers, c) the execution of drillings and the installation of inclinometers and d) the execution of a drilling and the installation of a piezometer. In progress are the works for the construction of guide walls for the station and access 2, bentonite manufacturing for the construction of DWs, the mobilization and setting-up of equipment for the construction of DWs and the construction of steel reinforcement cages for DWs (2 pieces). In progress are also the works for the execution of drillings and the installation of inclinometers at Entrances 1 and 3, as well as the works for the cutting of tree branches in the area of ISAP warehouse;

DIMOTIKO THEATRO Station: In progress are waterproofing works in Aghios Konstantinos Square and temporary retaining works (shotcrete - pre-stressed anchors - fully-embedded anchors) at the station’s 2nd excavation floor (+5.00) on Korai Square. Investigation works for identifying ancient wells/ tanks and dismantling works at P. Bakogianni Square are in progress. Works for the extension of the fencing are in progress. Excavation and temporary retaining works concerning the 5th level (-9.00) are also in progress at Deligianni Shaft, as well as archaeological investigation works in the areas where networks are being diverted. Construction works for the diversion of a sewage network in Panepistimio Shaft are also in progress;

Phase A excavation works (left half-section) for the 1st set of spiles are in progress. The progress of phase A boring works for the triple track NATM tunnel with direction to Piraeus has reached 1.5/140m. Phase A excavation works (right half-section) for the 1st set of forepoling beams has reached a progress rate of 8/63 with direction to the Municipal Theatre;

Tunnel boring works have been completed by 47%.

February 2015





















AGHIA VARVARA Station: Column construction works up to the roof level are in progress;

KORYDALLOS Station: Waterproofing, permanent lining reinforcement and concreting works are in progress;

NIKEA Station: Column concreting works from platform level -3 to the concourse slab at level -2, as well as works for the concreting of the NATM tunnel side walls have been completed. In the framework of the main Station’s permanent lining construction, concreting works are in progress for the columns from the concourse slab level to the E/M floor level, for a portion of the E/M slab, for the staircases nos. 6 and 7 and for the outer perimeter walls and columns from the E/M floor level to the roof slab level. In addition, works for the construction of the permanent lining of the main Station’s NATM tunnel are in progress (concreting of tunnel vault);

MANIATIKA Station: Excavation works for the main building of the Station (access ramp area) are in progress in the open trench area on P. Mavromichali Street, as well as the works for the excavation and phase A2 temporary retaining (north face – eastern gallery) of the Station’s main tunnel;

PIRAEUS Station: The works for the installation and assembly of the bentonite system, the arrival of accessories to be used in the construction of the diaphragm walls (DW) and the construction of guide walls for the DW testing panel to the north of the Station are in progress. At Entrance 3, in progress are the works for a) the demolition of ISAP perimeter fencing wall parallel to the earlier Akti Kallimasioti Street, b) the dismantling of the metal elements of the roof of ISAP warehouses building located at the opposite side of ISAP’s entrance on Kononos Street, and c) the demolition of the stone wall of the same building (1st building area). In the framework of PUO networks diversions, the works for the construction of 315 and 630 sewage network are also in progress. Moreover, in the framework of the traffic arrangements, the following works are also in progress: a) for the extension of the worksite occupation/ fencing (unification of Entrance 1 existing worksite area with the earlier Akti Kallimassioti street - occupation of the entrance of Grigoris coffee shop and occupation of part of Loudovikou Street), b) for laying of cables, c) for the connection of ILPAP network and removal of masts, d) for the construction of sidewalks (pumping station area, east sidewalk - south), and d) for dismantling the OASA stop located on the earlier Akti Kallimassioti street;

DIMOTIKO THEATRO Station: In progress are the excavation and temporary retaining works (shotcrete - pre-stressed anchors - fully-embedded anchors) in the area where the access ramp is to be dismantled, as well as the works for the temporary drainage at the station’s final excavation floor (1st section, 30m deep) on Aghiou Konstantinou Square. The works for the construction of the head beam above the station NATM connecting tunnel, at Korai Square, and dismantling works at P. Bakogianni Square are in progress. Excavation and temporary retaining works concerning the 4th level are also in progress, as well as the construction of the temporary floor and its temporary drainage, enabling the commencement of phase A excavation works for the NATM triple track tunnel at Deligianni Shaft. Finally, tunnel boring works for the 3rd tunnel interstation between KORYDALLOS and NIKEA Stations are in progress;

Tunnel boring works have been completed by 43%.

January 2015


























AGHIA VARVARA Station: The works for the construction of the mechanical floor slab are in progress;

KORYDALLOS Station: Concreting works of the Station foundation slab and perimeter walls up to the concourse level are in progress;

NIKEA Station: In the framework of the construction of the main Station permanent lining, concreting works for part of the platforms slab, part of the concourse slab extending between axes A-B and 5-6 and part of the E/M slab extending between axes D-E and 11-14 are in progress. In addition, the works for the construction of the permanent lining of the main Station NATM tunnel are in progress (concreting of lateral walls);

MANIATIKA Station: At the main building of the Station, excavation works for the 1st, 2nd, 3rd and 4th levels (access ramp area) are in progress, while shotcreting works at the 1st and 2nd levels (access ramp area) and pre-stressed anchors construction works at the 1st and 2nd levels are also in progress. Excavation works and phase A1 temporary retaining works (south face – eastern gallery, north face – western gallery) at the Station main tunnel are also in progress;

PIRAEUS Station: The works for the construction of the guide walls and the diaphragm walls slurry reservoir in the Station are in progress, while the works for the construction of the guide walls at Entrance 2 and the works for the diversion of the sewage network at ISAP building in Entrance 3 are also in progress. In the framework of PUO networks diversions, the works for the diversion of PPC LV network and the diversion of sewage, water supply, forthnet, hol networks and the construction of an 315 sewage pit are also in progress. Moreover, the works related to the re-configuration of the worksite occupation/ fencing, the construction of ILPAP network and the installation – removal of bollards and the installation of traffic signs, in the framework of traffic arrangements, are in progress. At Roloi Shaft, archaeological excavation is in progress;

DIMOTIKO THEATRO Station: Excavation works and the works for the implementation of the temporary retaining (shotcrete - pre-stressed anchors - fully-embedded anchors) at the 5th, 6th and 7th excavation levels in the area of the access ramp at Aghiou Konstantinou Square are in progress. The works for the installation of a temporary retaining (shotcrete) system at the 2nd excavation bottom (+6,00) in Korai Square are in progress. On 13/01/15, the Central Archaeological Council opined on the non preservation of the archaeological finds in P. Bakogianni Square. Excavation and temporary retaining works for the 4th level and the construction of beams at the headwalls of Deligianni Shaft are also in progress;

Tunnel boring from KORYDALLOS to NIKEA Station is in progress, whilst boring-installation and grouting works for the 1st series of spiles (31/36) at the triple-track NATM tunnel with direction towards the University of Piraeus are also in progress. Boring-installation and grouting works for the 1st series of forepoling beams (38/43) with direction to Dimotiko Theatro (Municipal Theatre of Piraeus) are in progress;

Tunnel boring works have been completed by 37%.

December 2014

















AGHIA VARVARA Station: The works for the construction of columns up to the mechanical floor level are in progress;

KORYDALLOS Station: Concreting works of the foundation slab and the perimeter walls of the Station up to the concourse level are in progress;

NIKEA Station: The works for the construction of the Station’s permanent lining are in progress (concreting of exterior perimeter walls and columns from level -3 of the platforms up to level -2 of the concourse slab, from level -2 of the concourse slab up to level -1 of the E/M slab, as well as concreting of the concourse slab);

MANIATIKA Station: The following works are in progress: Excavation and shotcreting of the Station’s main building at levels 6, 7, 8, 9, 10 and 11, construction of prestressed anchors of the Station’s main building at level 8, as well as works for the construction of fully embedded rock anchors in the C/C area at Petr. Mavromichali street. Excavation and temporary retaining works at the access chamber were completed, while excavation and temporary retaining works are in progress in the Station’s main tunnel (phase A1 – southern section – eastern gallery);

PIRAEUS Station: Foul water sewage works are in progress, while in the framework of traffic arrangement, works for the construction of ILPAP network and sidewalks are in progress;

DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) is in progress at excavation level 7 (-15.00), except the access ramp area at Aghiou Konstantinou square. The following works are in progress: excavation and temporary retaining at level 3 of Deligianni shaft, dismantling at Tsamadou street section for the diversion of PUO networks at Panepistimio shaft, as well as archaeological investigation works in the dismantling areas;

The tunnel boring machine is under maintenance at KORYDALLOS Station, while excavation works are expected to commence in the immediate future.

October 2014




















AGHIA VARVARA Station: The works for the construction of supporting columns up to the concourse level were completed, while the works for the construction of beams and the concourse slab are in progress. Moreover, the works for the construction of piles at Taxiarchon shaft are in progress;

KORYDALLOS Station: The works for the waterproofing of the Station up to the roof level, as well as the reinforcement and concreting works at the concourse level are in progress;

NIKEA Station: The works for the temporary drainage and waterproofing of the NATM tunnel invert of the main Station were completed. The works for the construction of the permanent lining of the main Station (exterior perimeter parapet walls and columns at level -3 of the platforms up to level -2 of the concourse slab) are in progress;

MANIATIKA Station: The works for the excavation and temporary retaining of the Station’s main building, as well as the excavation and temporary retaining works in the main Station tunnel are in progress;

PIRAEUS Station: The works for the diversion of OTE optic fibre networks and other providers, PPC and storm water networks are in progress. In the framework of traffic arrangements, the works for the construction of the traffic signalling network are in progress. The investigation trench for the identification of the foundations of the pedestrian bridge, as well as the investigation trenches in view of confirming ISAP building foundation items are in progress;

DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) are in progress at the 5th excavation level (-4.00), except for the access ramp area at Aghiou Konstantinou square. The excavation and temporary retaining works at the 1st level, at Deligianni Shaft, and the works for the installation of signs in the framework of implementing the traffic arrangements for the occupation of Tsamadou street, at Panepistimio Shaft, are in progress;

The tunnel excavation has been completed at a proportion of 26%.

September 2014













AGHIA VARVARA Station: The works for the construction of supporting columns up to the platform level were completed, while the works for the construction of parapet walls and the platform floor are in progress;

NIKEA Station: The works for the temporary drainage of the final excavation floor of the main Station, the waterproofing of the foundation slab of the main Station, as well as the excavation and retaining of the NATM tunnel of the Station were completed (Phase A’). The works for the waterproofing of the exterior perimeter parapet walls, the construction of the permanent lining of the main Station (concreting of the foundation slab at level -3 of the platforms) and the excavation and retaining of the Station’s NATM tunnel (Phase B’) are in progress;

MANIATIKA Station: The works for the excavation up to level 11, the laying of shotcrete at levels 4, 8 and 10 and the construction of prestressed anchors at level 4 of the Station’s main building are in progress;

PIRAEUS Station: The works for the routing of OTE optic fibre networks, various suppliers and PPC at the northern side are in progress. In the framework of traffic arrangements, the construction of road and asphalt pavings, the construction of the temporary fencing wall in OLP area and the installation of balustrades in OLP area have been completed. The works for the extension of the worksite occupation / fencing, the construction of sidewalks and traffic islands, the installation of traffic signs and the construction of traffic diversion parapet wall are in progress;

DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) were completed at the 3rd excavation bottom (+2.00), while the excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) at the 4th excavation level at Aghiou Konstantinou square are in progress. The works for the construction of temporary retaining piles have been completed, while the construction of a cap beam at Deligianni shaft and the archaeological excavation at the ventilation shaft are in progress;

The tunnel excavation has been completed at a proportion of 22%.

August 2014
































NIKEA Station: The works for the construction of a foundation earthing system, soil improvement works and works for the acceptance of the main Station foundation invert have been completed. Excavation works and works for the removal of the muck (removal of the excavated material from the Station NATM tunnel access), as well as works for the waterproofing of the foundation slab and perimeter walls, the construction of the main Station permanent lining (concreting of the foundation slab from axes 8-12) and the excavation and retaining of Station NATM tunnel (phase A) are in progress;

MANIATIKA Station: Excavation works up to level 9, shotcrete application up to level 8, the construction of pre-stressed anchors up to level 8 of the Station main building and the construction of fully embedded rock bolts are in progress;

PIRAEUS Station: The works concerning EPA, water-supply, OTE networks and other providers’ networks within the OLP area, as well as the connections of the natural gas pipe transverse to Akti Kallimasioti have been completed. In the framework of the traffic arrangements, the removal of stop sheds and ticket issuing offices, as well as the works for the relocation of the kiosk located at the west sidewalk at the south end of the diversion has been completed. Moreover, the construction of water-supply networks, slabs for storm-water duct protection and the construction of manholes for the water-supply network and OLP valves have been completed. The works for the extension of the worksite occupation surface/ fencing, the construction of road-paving layers (base, sub-base), the construction of a temporary wall for OLP’s fencing, the construction of OLP balustrades and the relevant protection for OTE and PPC networks are in progress;

DIMOTIKO THEATRO Station: The works for the excavation and installation of a temporary retaining system (shotcrete – pre-stressed anchors)/ 1st excavation bottom (+10.00) have been completed, while the archaeological investigations for ancient wells and tanks, the preservation of the Project’s archaeological finds, and the excavation and installation of a temporary retaining system (shotcrete – pre-stressed anchors) for the 2nd excavation level in Aghiou Konstantinou Square are in progress. The works -in the framework of the archaeological excavations- for the removal of earth from the trench at the Ventilation Shaft are in progress;

The works for the detachment of archaeological finds (pebbled floor) for preservation purposes have been completed, while the works for the construction of temporary retaining piles in Deligianni Shaft are in progress;

Tunnel excavation works have been completed by 17%.

July 2014















AGHIA VARVARA Station: The works for the construction of the platform columns and floor slab are currently in progress;

KOLYDALLOS Station: Completion of the works related to the drilling, embedding and tensioning of the pres-stressed anchors, as well as of the Station’s raft concreting works;

NIKEA Station: In progress are the works for the construction of the Foundation Earthing, as well as for the temporary drainage of the floor of the final excavation level of the main Station’s C/C part (axes 8-15);

MANIATIKA Station: Completion of the pile cap beam construction works - In progress are the works for the excavation of the 7th and 8th levels, the application of the shotecrete and the construction of the pre-stressed anchors at level 7 of Station’s main structure;

PIRAEUS Station: Completion of the drilling operations for the construction of a water-jet drilling, the installation of piezometers and trial pumping at access 3, as well as the works for the demolition of three small buildings. The works for dismantling gates E5 and E6 are also completed. Still in progress are the works for the construction of the natural gas pipe networks at the location where PUO diversion works are executed. Moreover, in the framework of the traffic arrangement, completion of the construction of the industrial floor and the water supply manholes in view of changing the ships mooring location, the arrangement of EYDAP’s pumping station corridor and the configuration of the surrounding area, the construction of new walkways in the area of Gate E7 and the relocation of OLP’s lighting pole; at the same time, in progress are the works for the construction of the stormwater drainage network, the construction of traffic lights network, the construction of ILPAP network and the construction of the street lights;

DIMOTIKO THEATRO Station: Completion of the works for the construction of piles and pile cap beams at Aghiou Konstantinou square, as well as of the works for the construction of the temporary retaining piles at Korai Square;

Completion of EYDAP network diversion works at Deligianni Shaft; completion of dismantling/removal works in the section located inside the yard area of the University at Panepistimio Shaft; archaeological excavations in this area are in progress;

Commencement of the tunnel boring operations for the 2nd interstation; 12% completed so far.

June 2014



 

 

 

 












 


NIKEA Station: The excavation and muck disposal, as well as the construction of the temporary retaining (shotcrete, prestressed anchors, metal struts) at levels 5 and 6 of the main Station were completed. The excavation and disposal of excavation spoils of the main Station (levels 7, 8 and final excavation level), the construction of prestressed anchors of levels 7 and 8 of the main Station, the laying of shotcrete at levels 7, 8 and at the final excavation level of the main Station, the improvement and acceptance of the final excavation floor of the main Station’s C/C and the construction of NATM tunnel (Phase A’) of the Station are in progress;

MANIATIKA Station: The excavation, the laying of shotcrete and the construction of prestressed anchors at level 6 of the Station’s main building are in progress;

PIRAEUS Station: The worksite occupation / fencing of a part of access 2 and the diversion of fiber optics C4i, fiber optics of OLP/PPC/water supply and natural gas in OLP area were completed. Moreover, the construction of a temporary bridge at the NW edge of the pier, the installation of new passenger waiting areas, new WCs at new locations and the reduction of the sidewalk width at Kononos street, as well as the construction of new curbs were completed;

DIMOTIKO THEATRO Station: The construction of the building crane and the archaeological excavation at Aghiou Konstantinou square were completed, while the works for the reinstatement of the Archaeological Service building to be utilized for the storage, conservation and transfer of archaeological finds of the Project are in progress. The works for the construction of temporary retaining piles (33/51 piles) in Korai square are in progress;

The archaeological excavation at Deligianni Shaft was completed. The Central Archaeological Council (CAC) gave its expert opinion on the preservation of the pebble floor and the non-preservation of the remaining archaeological finds. The preparation of the design concerning the detachment of archaeological finds listed for preservation (pebble floor) was completed, while the works for the detachment of the subject finds are in progress;

The TBM maintenance works is completed prior to the commencement of the excavation works at the 2nd interstation.

May 2014



















KORYDALLOS Station: The works for the general excavation of the Station and the works for the improvement of the foundation invert – placement of a drainage layer have been completed. Waterproofing works, the works for the placement of reinforcement and foundation slab concreting works are in progress.

NIKEA Station: Excavation works and the works for the removal of the excavation spoils from the 1st up to the 4th level of the station have been completed. Excavation works, the works for the removal of the excavation spoils, concreting works at the 4th up to the 8th level and at the final excavation level are in progress. The works for the permanent lining of the main Station are also in progress.

MANIATIKA Station: The works for the diversion of PUO networks (sewage, water-supply, telephony, power supply), excavation works at the 4th and the 5th level of the main building of the station, shotcreting works and works for the construction of prestressed anchors at the 3rd, 4th and 5th level have been completed.

PIRAEUS Station: The investigation trench drilled to locate the foundations of ISAP building has been completed, as well as the archaeological investigation trenches in a section of access 2 and the works for the dismantling of the sheds in access 2. The works for the dismantling of existing structures, as well as works for the excavation of archaeological investigation trenches in access 3 have also been completed.

DIMOTIKO THEATRO Station: The archaeological works and works for the construction piles for temporary retaining are in progress. The archeological investigation and the excavation works at the perimeter of the excavation in Korai Square have been completed. The archaeological works in Bakogianni Square are in progress.

Tunnel boring works have been completed by 7%.

April 2014


 



 

 

 




 


The works for the construction of cap beam, excavation and temporary retaining, temporary drainage of the raft and the construction of the foundation slab are completed, while waterproofing works and works for the construction of walls are in progress at AGHIA VARVARA Station;

The worksite fencing, as well as the archaeological investigation trenches at Taxiarchon Shaft of AGHIA VARVARA Station, were completed;

The works for the construction of piles and the cap beam at KORYDALLOS Station were completed, while the general excavation at the final level is at the final level (level 7);

The works for the construction of piles and the cap beam, as well as the temporary retaining of NIKEA Station, were completed, while waterproofing works of the foundation slab and the construction of prestressed anchors are in progress (levels 4 to 8);

The works for the construction of piles and the archaeological excavation were completed, while the excavation at levels 2 and 3 are in progress at the main building of MANIATIKA Station;

The worksite occupation for the PUO diversions, as well as the diversion of the gas pipe in OLP area at PIRAEUS Station are completed. Moreover, the investigation archaeological trenches for the identification of ISAP building sewage pipe were completed;

The relocation of PUO networks, as well as the installation of a building crane were completed, while the works for the construction of temporary retaining piles at Aghiou Konstantinou square, at DIMOTIKO THEATRO Station, are in progress;

The tunnel excavation has been completed to 5%.

March 2014





The works for the construction of the temporary retaining piles at AGHIA VARVARA Station are completed, while the works for the temporary discharge of the invert and the waterproofing works are in progress;

The installation of the drainage layer on the invert of KORYDALLOS Station is in progress;

The drainage of the final floor of NIKEA main station C/C excavation is in progress;

The works related to the excavation of the 1st and 2nd levels of MANIATIKA Station main building, as well as the construction of prestressed anchors, are in progress.

February 2014








The archaeological investigation trenches in Komninou Shaft were completed;

The works for the construction of the foundation slab in AGHIA VARVARA Station are in progress;

The general excavation works at the final level of KORYDALLOS Station are at an advanced stage;

Shotcrete works up to the 8th level of NIKEA Station are at an advanced stage;

The works for the diversion of the sewage water network, PPC, EPA, water supply, OTE optic fibres and supplies in Piraeus Port Authority S.A. (OLP) area in PIRAEUS Station are in progress;

The works for the transfer of the archaeological finds in a storage and conservation room, as well as the installation of a building crane at Aghiou Konstantinou square, at DIMOTIKO THEATRO Station, are in progress.

January 2014



The general excavation (6th level) along with the temporary retaining structures in the area of KORYDALLOS Station are at a completion percentage of 89%;

The worksite fencing in TAXIARCHON Shaft in AGHIA VARVARA Station is in progress;

The main excavation works in the area of NIKEA Station (C/C) is at percentage of 66%, while the construction of pre-stressed anchors is at percentage of 72%;

The construction of piles in the area of MANIATIKA Station is in progress.


WATCH HERE THE PROJECT PROGRESS FOR 2013

WATCH HERE THE PROJECT PROGRESS FOR 2012
   
 
Print this page E-mail this page
    Last Updated: 11/8/2015
 
     
                                                         

   