Year: 2016

February 2016

In progress are the relocations of the water supply networks at the sidewalk adjacent to Grigoriou Lambraki street, OTE & Fiber Optics networks at Ethn. Antistaseos street, Sewage & EPA networks at Omiridou Skylitsi street & street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk…
Μάθε Περισσότερα

February 2016

Dimokratias Crossover: The works for the construction of level -2 were completed, while the preparation for the excavation of level -3 is in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. SINTRIVANI Station: Preparatory works for the excavation of level -4 are in progress.…
Μάθε Περισσότερα

February 2016

NOMARCHIA Station: The works for the installation of metal struts at level -1 were completed, while the excavation of the station’s level -2 is in progress. NOMARCHIA Crossover: The works for the installation of metal struts at level -1 are in progress. KALAMARIA Station: Works for traffic arrangements – Phase…
Μάθε Περισσότερα

January 2016

AGHIA VARVARA Station: The works for the waterproofing, construction of walls and platform floors, of perimeter walls up to the ticket issuing level, as well as the works for the construction of walls up to the roof level are in progress. Taxiarhon Shaft: The excavation works along with the works…
Μάθε Περισσότερα

January 2016

Completed are the relocations of sewage, PPC & and EPA networks at the sidewalk adjacent to Grigoriou Lambraki street, Sewage, EPA & Fiber Optics at Vassileos Georgio street and the ILPAP abolished lines dismantling works at Vassileos Georgiou street. In progress are the relocations of the water supply networks at…
Μάθε Περισσότερα

January 2016

PATRIKIOU Station & Crossover: The works for the construction of diaphragm walls are in progress. VOULGARI Station: The works for the POY network diversions, traffic arrangements and worksite installations are in progress. NEA ELVETIA Station & Crossover: At the crossover, the construction of the foundation slab is completed, while the…
Μάθε Περισσότερα

January 2016

NOMARCHIA Station: The excavation of the station’s level -1 is completed, while the works for the installation of metal struts at level -1 are in progress. NOMARCHIA Crossover: The excavation of the crossover’s level -1 is completed, while the works for the installation of metal struts at level -1 are…
Μάθε Περισσότερα

THESSALONIKI METRO – The Metro Project is back to track. The contract for the execution of archaeological excavations was signed today

Further to the negotiations lead by the Minister of Infrastructures, Transport and Network Mr. Christos Spirtzis with the Contracting Joint Venture of Thessaloniki Metro, the following activities are being developed: PATRIKIOU, NEA ELEVETIA, VOULGARI Stations and the Depot at the east end of the Metro Base Line are being constructed…
Μάθε Περισσότερα