Month: June 2011

June 2011

The first TBM continues its underground journey and has already covered a distance of 318m. past EFKLIDIS Station. The construction of the 2 underground levels of FLEMING Station has been completed, while the concreting works of the station shafts are in progress. The works for the construction of the pits…
Μάθε Περισσότερα

May 2011

The works for the cleaning and maintenance of the cutter heads and the remaining facilities pertaining to the two Tunnel Boring Machines are at a completion stage. The works for the construction of EFKLIDIS Station shafts are in progress. Jet grouting works along ANALIPSI Station have been completed.
Μάθε Περισσότερα