Day: April 22, 2013

March 2013

The works for the construction of temporary retaining piles and the pile cap beam at the TBM start-up shaft have been completed; The works for the dismantling of shop sheds, as well as for the construction of new sidewalks at the eastern and southern part of Eleftherias square at KORYDALLOS…
Μάθε Περισσότερα

March 2013

The works for the construction of shafts and accesses in PANEPISTIMIO Station area are in progress. The construction of the 1st level slab has been completed in SYNTRIVANI Station area. The works for the construction of the underground strut using the jet grouting method are in progress in ANALPSI Station…
Μάθε Περισσότερα