Month: September 2015

August 2015

AGHIA VARVARA Station: The construction works and the works for stressing the prestressed anchors at Taxiarchon Shaft are about to be completed; KORUDALLOS Station: The works for waterproofing the station are in progress; NIKEA Station: The TBM maintenance works are in progress; PIRAEUS Station: The works for the construction of…
Μάθε Περισσότερα

August 2015

Completed are the relocations of OTE networks at the sidewalk of Grigoriou Lambraki street adjacent to the Tramway corridor and the dismantling of ILPAP networks from Ethnikisi Antistasseos Street. In progress are the relocations of sewage and EPA networks along with the archaeological works at Vassileos Georgiou street, as well…
Μάθε Περισσότερα

August 2015

NOMARCHIA Station: The works for the construction of retaining piles at the perimeter of the station were completed. The works for the construction of a pile cap beam are in progress; KALAMARIA Station: Works for the construction of piles at the western part of the station are in progress; NEA…
Μάθε Περισσότερα