Month: April 2016

March 2016

AGHIA VARVARA Station: The construction of the ticketing level slab was completed. At Taxiarchon shaft, the excavation of the 7th level was completed. NIKEA Station: The works for the permanent lining of the station were completed. More specifically: construction of the invert (reverse arch) construction of side walls construction of…
Μάθε Περισσότερα

March 2016

In progress are the relocations of OTE & Fiber Optics networks at Ethn. Antistaseos street, street lighting at the sidewalk adjacent to Grigoriou Lambraki street and at the sidewalk adjacent to Ethnikis Antistasseos street. The water supply works commenced by EYDAP and are in progress at the sidewalk adjacent to…
Μάθε Περισσότερα

March 2016

Dimokratias Crossover: The works for the excavation of the final level -3 are in progress. DIMOKRATIAS Station: Preparatory works for the excavation of level -3 are in progress. AGHIA SOFIA Station: The works for the construction of anchors for the temporary retaining of the southern access and the general excavation…
Μάθε Περισσότερα

March 2016

NOMARCHIA Station: The works for the installation of metal struts at level -2 are in progress. NOMARCHIA Crossover: The works for the installation of metal struts at level -1 were completed. The excavation works of level -2 and the works for the installation of metal struts at level -2 are…
Μάθε Περισσότερα