Day: May 19, 2017

April 2017

NOMARCHIA Station: The permanent lining at level -1 has been completed. Works for the construction of the slab at level -2 are in progress. • KALAMARIA Station: The construction of the permanent lining at level -3 has been completed. The construction of the slab at level -2 is in progress.…
Μάθε Περισσότερα

April 2017

• NEW RAILWAY Station: The archaeological excavation at the south shafts is complete. The excavation and the temporary retaining of the southern shaft are in progress. • DIMOKRATIAS Station: The construction of the temporary retaining at the southern access is in progress. • SINTRIVANI Station – EXPO: The construction of…
Μάθε Περισσότερα

April 2017

• At Ethnarhou Makariou street, the construction of the staircase connecting Karaiskaki stop with the underground pedestrian walkway has been completed. • At Lambraki bridge, the construction of the pedestrian bridge and the widening of the sidewalk are in progress. • At Grigoriou Lambraki street, the tramway corridor from the…
Μάθε Περισσότερα

April 2017

• Along the double track tunnel, from the beginning of the extension up to TBM startup shaft, the permanent lining of the tunnel invert has been completed, while the works for the permanent lining of the tunnel vault are in progress. • AGHIA VARVARA Station: Works for the construction of…
Μάθε Περισσότερα